7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Oscar GlorySheth BuildtechDue Apr 2027, extended 4 mo——
Shree Trambakraj HillsShree BuildconDue Jul 2028, extended 4 mo——
Sudarshan EmpireSudarshan Keru SangaleDue Mar 2030, extended 4 mo——
Mitansh ArcadeDilip ConstructionDue Apr 2028, extended 4 mo——
Seven ColorsSeven ColorsDue Oct 2028, extended 4 mo——
Siddharth BlossomRajmohini AssociatesDue Mar 2028, extended 4 mo——
Satkar ResidencyAnand Shanker RaiDue Apr 2027, extended 4 mo——
Ashtapad Phase VIIArkk Builders And DevelopersDue Apr 2030, extended 4 mo——
Patwardhan ApartmentRaviraj BuildtechDue Apr 2027, extended 4 mo——
Aakar CrestAakar Developers6 mo late——
Gokul NineGokul InfratechDue Apr 2029, extended 4 mo——
Narayan HightsMauli Construction And DevelopersDue Apr 2029, extended 4 mo—45%
Samruddhi VillaSanskar Builders And DevelopersCompleted——
Vasant Vihar Apartment Co. Op. Housing SocietyKeystone ConstructionDue Oct 2028, extended 4 mo——
Ayodhya ResidencyAkshay Subhash KhalkarDue Apr 2030, extended 4 mo——
Om PlazaBS ConstructionDue Apr 2028, extended 4 mo——
Palm Hills 03Sarvppratham Developers Private LimitedDue Apr 2028, extended 4 mo——
Sukhvastu ApartmentS M AssociatesDue Apr 2031, extended 4 mo——
Gajanan Nest - Wing A, B, CJaiprasad constructions and developers LLPDue Apr 2032, extended 4 mo——
Karnish ParkVinayak Premises Pvt. LtdDue Apr 2028, extended 4 mo——
Samarth ParkPrathamesh Constructions And Developers11 mo late——
Shree Sai PalaceShree Sai BuildconDue Apr 2028, extended 4 mo——
Unity TowerUnity ConstructionsDue Apr 2028, extended 4 mo——
Chandani Co. Op. Housing SocietyShivaay BuildconCompleted——
Livin SolitaireThe Livin SpacesDue Jul 2027, extended 4 mo——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology