RERA projects in Vilholi

1 project under 1 MahaRERA registration, registered 2022–2022. 100% have a completion date extended beyond the one promised.

Locality
1RERA projects
1Registrations
0Completion still due1 past their completion date
6 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20221

Projects in Vilholi

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Pavan Park A WingGodse CorporationP5160004535112 May 202231 Dec 202330 Jun 2024Extended 6 mo0

Other localities in Nashik

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Godse Corporation1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology