RERA projects in Jail Road
55 projects under 55 MahaRERA registrations, registered 2017–2026. 4% have a completion date extended beyond the one promised.
Locality
55RERA projects
55Registrations
12Completion still due43 past their completion date, 6 marked completed
14 monthsMedian extension beyond promised date4% of registrations extended
2Regulatory caseson 2 projects
14Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 10 |
| 2018 | 2 |
| 2019 | 8 |
| 2020 | 6 |
| 2021 | 7 |
| 2022 | 10 |
| 2023 | 7 |
| 2024 | 2 |
| 2025 | 2 |
| 2026 | 1 |
Projects in Jail Road
55 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Amrut Kalash ApartmentSwastik Estates | PR1220002502640 | 9 Mar 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Krishna Kunj ApartmentAnup Buildcon | PM1220002501024 | 1 Oct 2025 | 1 Jun 2030 | — | Not yet due | 0 |
| Shiv Vitthal ResidencyJagale Construction | P51600080121 | 29 Apr 2025 | 31 Mar 2030 | — | Not yet due | 0 |
| Sangamnere ComplexVishal Builders And Developers | P51600077046 | 16 Jul 2024 | 31 Dec 2028 | — | Not yet due | 1 |
| Aaradhy Classic Building No.2Siddhi Corporation | P51600055370 | 22 Mar 2024 | 15 Oct 2028 | — | Not yet due | 0 |
| Shubh Kalash ApartmentSwastik Estates | P51600050886 | 15 May 2023 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Datta Prem ApartmentPremchand Nimbaji Patil | P51600050475 | 17 Apr 2023 | 31 Aug 2026 | — | Promised date passed | 0 |
| Jay Prakash Co. Hsg. SocietyJ B Developers | P51600049535 | 15 Feb 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Vihan HeightShahane Infra Builders And Developers | P51600048950 | 24 Jan 2023 | 31 Jan 2025 | — | Promised date passed | 0 |
| VijayshrushtiVrv Construction | P51600049003 | 24 Jan 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Gajanan HeightsAditya Vasudev Pund | P51600048530 | 6 Jan 2023 | 1 Dec 2025 | — | Promised date passed | 1 |
| Matrudham Co-Op Housing SocietyMatrudham Co-Op Housing Society | P51600048418 | 3 Jan 2023 | 31 Jul 2027 | 31 Jul 2027 | Not yet due | 0 |
| Snehsansar Co-Op Hsg Society LtdH M Builders | P51600047563 | 9 Nov 2022 | 1 Jun 2024 | — | Promised date passed | 0 |
| Para AvenueKishan Pokar | P51600046633 | 25 Aug 2022 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| Sai Kalash ApartmentSwastik Estates | P51600046015 | 15 Jun 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Narayan Co-Operative Housing Society Ltd.Narayan Infra | P51600034888 | 28 Apr 2022 | 31 Mar 2025 | — | Promised date passed | 0 |
| Vaishali GoldShree Ganesha Buildcon | P51600034356 | 4 Apr 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Sky GloryShree Sadguru Buildcon | P51600034302 | 30 Mar 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Sai ApartmentSai Developers | P51600033144 | 9 Feb 2022 | 1 Jan 2025 | — | Promised date passed | 0 |
| Nandan ResidencySahej Builders And Developers LLP | P51600033017 | 3 Feb 2022 | 1 Jan 2029 | — | Not yet due | 0 |
| Swara HeightsSiddhraj Buildtech | P51600032746 | 24 Jan 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Om Shree ShrushtiShree Om Buildcon | P51600032679 | 17 Jan 2022 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Chandra TaraPremchand Nimbaji Patil | P51600032151 | 14 Dec 2021 | 31 Oct 2024 | — | Promised date passed | 0 |
| Pawar ComplexShree Sai Ganesha Infrastructure | P51600032185 | 14 Dec 2021 | 31 Dec 2023 | — | Promised date passed | 0 |
| Guru VillaGurujyot Enterprises | P51600030961 | 29 Sep 2021 | 18 Aug 2024 | — | Promised date passed | 0 |
Other localities in Nashik
Most active promoters
By projects registered here, as named on MahaRERA.
- Swastik Estates5 projects
- Dinesh Eknath Khandre2 projects
- Premchand Nimbaji Patil2 projects
- Shree Om Buildcon2 projects
- Aditya Vasudev Pund1 project
- Ajit Suresh Bane1 project
- Anup Buildcon1 project
- Arun Devidas Patil1 project
- Avinash Omprakash Yadav1 project
- Ganraj Residency Co-Op Housing Society Ltd1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology