RERA projects in Deolaligaon
64 projects under 65 MahaRERA registrations, registered 2017–2026. 14% have a completion date extended beyond the one promised.
Locality
64RERA projects
65Registrationssome projects hold several
20Completion still due45 past their completion date, 3 marked completed
12 monthsMedian extension beyond promised date14% of registrations extended
4Regulatory caseson 4 projects
8Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 15 |
| 2018 | 5 |
| 2019 | 3 |
| 2020 | 6 |
| 2021 | 7 |
| 2022 | 9 |
| 2023 | 9 |
| 2024 | 6 |
| 2025 | 3 |
| 2026 | 2 |
Projects in Deolaligaon
64 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| ABS Commercial ComplexAakruti Buildcon Private Limited | PC1220002601308 | 27 Jul 2026 | 30 Jun 2027 | — | Not yet due | 0 |
| Pm1220002503052Patil Epitome Pvt Ltd | PM1220002503052 | 27 Mar 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Surya Sunder Co-Op Hsg. Soc. Ltd.Narayan Infra | PR1220002501365 | 31 Oct 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Angarika Co Op Housing Society Ltd | P51600080915 | 13 Aug 2025 | 30 Jun 2028 | — | Not yet due | 0 |
| Varad HeightsVarad Associates | P51600080577 | 16 Jun 2025 | 31 Mar 2029 | — | Not yet due | 0 |
| Raghuveer ParkRNK Landmarks LLP | P51600078540 | 21 Dec 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Yamuna HeightsKiran Dinkar Kharjul | P51600056258 | 22 May 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Tanishq Park RoyalsM S Builders & Developers | P51600055929 | 29 Apr 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Symphony Co-Op Housing SocietyJ B Construction | P51600055437 | 22 Mar 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Rass Residency - Building ARass Developers | P51600054924 | 21 Feb 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Mukund Co-Op Housing SocietySamrat Buildcon | P51600054653 | 2 Feb 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Kesar ClassicKesar Infraspaces LLP | P51600054090 | 27 Dec 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Shiv Samarth ApartmentNitin Madhukar Jagale | P51600050492 | 17 Apr 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Shree Omkar AvenueShree Buildcon & Associates | P51600050493 | 17 Apr 2023 | 31 Aug 2027 | — | Not yet due | 0 |
| Divine ResidencyAniket Anant Patil | P51600050105 | 15 Mar 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Om ResidencyOm Developers | P51600050012 | 6 Mar 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Heramb ResidencyDinesh Eknath Khandre | P51600049119 | 30 Jan 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Devi Darshan Row HousesDales Realtors | P51600048982 | 24 Jan 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Serenity ParkSai Construction | P51600048887 | 24 Jan 2023 | 25 Nov 2025 | — | Promised date passed | 0 |
| Antarang ApartmentShrinath Realty | P51600048580 | 10 Jan 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Shivneri ResidencyNice Home | P51600048370 | 27 Dec 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Shree SocietyGanraj Infra | P51600047712 | 21 Nov 2022 | 31 Dec 2027 | — | Not yet due | 0 |
| Shree Bhagwati Co-Op Hsg SocietyVinay Maganlal Karnavat | P51600047578 | 9 Nov 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Star Plus BDeepak Kalyanji Chande | P51600045827 | 15 Jun 2022 | 31 Dec 2028 | — | Not yet due | 0 |
| Tulsi Tirth ApartmentMakani Buildcon | P51600045678 | 6 Jun 2022 | 31 Dec 2028 | — | Not yet due | 0 |
Other localities in Nashik
Most active promoters
By projects registered here, as named on MahaRERA.
- Kbc Global Limited4 projects
- Shree Sainath Land & Development (India) Private Limited3 projects
- Rishi Builders And Developers2 projects
- Sai Construction2 projects
- Shree Buildcon & Associates2 projects
- Aakruti Buildcon Private Limited1 project
- Abhay Chandmal Jain1 project
- A C Jain Builders And Developers LLP1 project
- Ajit Damji Pokar Huf Karta Ajit D Pokar1 project
- Akar Developers1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology