Vihitgaon, Nashik
Deedo IDDL-NSK-VIHITGAON5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects26
Registrations26
Completion still due1610 past their date
Median extension4 months54% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
26 MahaRERA registrations in Vihitgaon
4 not yet due12 extended, not yet due10 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Vihitgaon
26 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shree VishvaDilip Vishwanath Godse | Due Dec 2031 | — | — |
| Swastik HeightsTuljaa Realty | Due Apr 2030, extended 4 mo | — | — |
| Pravin Anand ApartmentPravin Rajaram Gaikhe | Due Jul 2030, extended 4 mo | — | — |
| Morya PridePalde Construction | Due Jan 2028, extended 4 mo | — | — |
| Ayodhya ResidencyAkshay Subhash Khalkar | Due Apr 2030, extended 4 mo | — | 0% |
| Sadguru HeightsSadguru Builders And Developers | Due Apr 2028, extended 4 mo | — | 0% |
| Madhav ParkM/S Kapse Developers | Due Nov 2027, extended 4 mo | — | 0% |
| NestKushavart Realtors | Due Nov 2026, extended 4 mo | — | 15% |
| Samarth PrabhatChandrakant Ramkrishna Godse | Due Dec 2026 | — | 18% |
| Ashtapad Phase VArkk Builders & Developers | Due Apr 2027, extended 4 mo | — | 58% |
| Palai Villas - Phase 2N D Developers | Due Apr 2030, extended 4 mo | — | 1% |
| Manokamneshwar ApartmentAkshay Balasaheb Mhaske | Due Apr 2027, extended 4 mo | — | 5% |
| Dream ParkHussain Babu Mulla | Due Apr 2031, extended 4 mo | — | 24% |
| Ashtapad HeightsArkk Builders And Developers | Due Apr 2027, extended 4 mo | — | — |
| Sai SamruddhiAkshay Subhash Khalkar | 1 yr 4 mo late | — | 100% |
| Madhav NiwasKapse Developers | 9 mo late | — | 0% |
| Arrpan HousingA C Jain Builders And Developers LLP | Due Nov 2026 | — | 68% |
| Sai ParkJay Developers | Due Dec 2026 | — | 49% |
| Ishwar Sankalp ABCDShankar Ghanshaymdas Samnani | 1 yr 7 mo late | — | 0% |
| Jinendra EstateOswal Developers | 4 yrs 10 mo late | — | 0% |
| Nest CastleNest Developers | 8 yrs 3 mo late | — | 50% |
| Palai VillasN D Developers | 5 yrs 10 mo late | — | 58% |
| Renuka PrasannaRenuka Devlopers | 7 yrs 10 mo late | — | 47% |
| Hari Laxmi Phase IIKbc Global Limited | 1 yr 10 mo late | — | 41% |
| Renuka DarshanRenuka Developers | 5 yrs 10 mo late | — | 52% |
Nearby: other localities in Nashik
Most active promoters
- Akshay Subhash Khalkar2 projects
- N D Developers2 projects
- A C Jain Builders And Developers LLP1 project
- Akshay Balasaheb Mhaske1 project
- Arkk Builders And Developers1 project
- Arkk Builders & Developers1 project
- Chandrakant Ramkrishna Godse1 project
- Dilip Vishwanath Godse1 project
- Hussain Babu Mulla1 project
- Jay Developers1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology