RERA projects in Satara

1,181 projects under 1,194 MahaRERA registrations across 126 localities, registered 2017–2026. 12% have a completion date extended beyond the one promised.

1,181RERA projectsin 126 localities
1,194Registrationssome projects hold several
389Completion still due599 past their completion date
22 monthsMedian extension beyond promised date12% of registrations extended
79Regulatory caseson 79 projects
99Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
2017227
201891
201986
202078
202196
202294
2023102
202467
202586
202661

Localities in Satara

By number of registered projects. Talukas and localities as MahaRERA names them.

All 126 localities

Projects in Satara

1,181 projects registered with MahaRERA in this district and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Dipankar PlazaDinpankar PlazaPC13000026021707 Oct 202630 Sep 2031—Not yet due0
Moraya VishwaKumar Balasaheb ChavanPR13000026021777 Oct 202631 Dec 2029—Not yet due0
Navnirrmitii SquareNavnirrmitii Builders And Developers LLPPM13000026021435 Oct 202631 Dec 2030—Not yet due0
Emerald HeightsVishal Dilip PawarPR13000026020681 Oct 202631 Dec 2032—Not yet due0
silver valleyDevashree Garden LLPPR13000026020981 Oct 202631 Aug 2030—Not yet due0
Tajcitrus ParkFiltrum Infrastructure Private LimitedPM13000026021051 Oct 202631 Dec 2031—Not yet due0
Sargam HeightsK K DevelopersPR130101260201123 Sep 202631 Mar 2032—Not yet due0
Tanush Park Phase IISamruddhi Builders & Developers, Abhijit Jadhav, Ranjit JadhavPR130101260201723 Sep 202631 Dec 2030—Not yet due0
Mangalmurti ComplexSankalp DevelopersPM130000260199622 Sep 202631 Dec 2032—Not yet due0
Sai Darshan ResidencyNitin Dasharath KapasePR130000260199722 Sep 202631 Dec 2029—Not yet due0
AnandnagarAnil Anandrao Shingan, Vidya Vishal Ingawale, Suman Anandrao ShinganPR130000260195917 Sep 20261 May 2029—Not yet due0
Digvijay Anandrao GaikwadKrishnaa InfraPM130000260190815 Sep 202630 Jun 2031—Not yet due0
Namo ResidencySarada Landmark Private LimitedPR130000260193415 Sep 202631 Dec 2032—Not yet due0
Raygad VandanKedareshwar Builders And DevelopersPR13000026018399 Sep 202631 Dec 2029—Not yet due0
Swades ResidencySaifullah Ilahi KhairatkhanPR13000026018409 Sep 202631 Mar 2029—Not yet due0
Panchratna CrystalShree Panchratna GroupPR13000026017904 Sep 202631 Dec 2029—Not yet due0
Shreeji EliteJagtap Devi AssociatesPR13000026017924 Sep 202631 Dec 2031—Not yet due0
Vedant LandmarkUnique DevelopersPM13000026017452 Sep 202631 Dec 2030—Not yet due0
Reliable EmeraldReliable BuildwellPR130000260171131 Aug 202631 Dec 2028—Not yet due0
Rohan Heights Phase IIIRohan BuildersPR130000260168427 Aug 202631 Dec 2031—Not yet due0
Radhakrushna EmpireShree Balaji Builders And DeveloperPR130000260159921 Aug 202630 Jun 2031—Not yet due0
Samarveer SkylineShri Mangalmurti BuildersPR130000260156317 Aug 202631 Dec 2033—Not yet due0
Vrundavan CityKalyani InfraPM1300002601449, PM13000026015077 Aug 20261 Jun 2030—Not yet due0
VantaraAvinash Namdeo ManePP13000026014375 Aug 202631 Dec 2029—Not yet due0
Rajashree TowersDivine SpacesPR13000026014134 Aug 202631 Dec 2027—Not yet due0
Swarngiri HeightsOmkar DevelopersPM13000026014234 Aug 20261 Mar 2031—Not yet due0
Reliable PrideReliable AssociatesPR13000026014023 Aug 202631 Dec 2031—Not yet due0
Akshay ParkAkshay Civil Engineers And ContractorsPR130000260134329 Jul 202630 Sep 2030—Not yet due0
Shree Keshav ResidencyShree Dwarka DevelopersPR130000260131727 Jul 202631 Dec 2030—Not yet due0
Anuraj Arcaed Tower DAnuraj ConstructionPR130000260129223 Jul 202631 Dec 2029—Not yet due0
Menlo FrontyardBlue Ladder Estates Private LimitedPP13000026010597 Jul 202631 Dec 2027—Not yet due0
Vimal ResidencyPrime DevelopersPR130000260094629 Jun 202631 Dec 2031—Not yet due0
Putalai VishwaLaxmi ConstructionsPR130000260081717 Jun 202631 Dec 2027—Not yet due0
VivantaD Cube Buildcon LLPPM130000260078715 Jun 202631 Dec 2029—Not yet due0
Dwarka CityHeramb InfraPM130000260072110 Jun 202631 Dec 2031—Not yet due0
Versatile VivaVersatile Housing & Infrastructure Private LimitedPP130000260072210 Jun 202631 Dec 2030—Not yet due0
Keyur ResidencyAmit Shantaram PatilPR13000026005891 Jun 202631 Dec 2031—Not yet due0
Prasad PridePrasad Builders And DevelopersPM130000260052625 May 20261 Dec 2032—Not yet due0
Viraj ParkVs InfraPR130000260054025 May 202631 Dec 2031—Not yet due0
Unique LandmarkAkshad Infrastructure And DevelopersPR130000260044717 May 202631 Dec 2030—Not yet due0
River CountyS B GroupPR130000260039411 May 202614 Feb 2032—Not yet due0
Heramb ResidencyVision DevelopersPR130000260028228 Apr 202631 Dec 2028—Not yet due0
Saavi The Heart Of VikasnagarSaavi The Heart Of VikasnagarPR130000260010315 Apr 202631 Dec 2030—Not yet due0
Indu EliteLandmark Builders And DevelopersPR130000260006810 Apr 202631 Dec 2030—Not yet due0
Bajirao EmpireShree Sheshachal DevelopersPR130000250305427 Mar 202631 Dec 2031—Not yet due0
Ranjit PlazaSkyline DevelopersPM130000250302824 Mar 202631 Dec 2030—Not yet due0
Narayan AshwiniAbasaheb Jare ConstructionPR130000250289718 Mar 202631 Dec 2030—Not yet due0
Anvi PearlAmol Barge And AssociatesPR130000250286617 Mar 202631 Dec 2031—Not yet due0
ShivsaiDream Vision PropertiesPR130000250284116 Mar 202631 Dec 2029—Not yet due0
Shriram PlazaBrahmachaitanya DevelopersPM130000250284216 Mar 202631 Dec 2030—Not yet due0
Moon Light TowerRaj BuildersPR130000250274912 Mar 202631 Dec 2030—Not yet due0
Sukhodayam VillasM/s Ultra Urban Greene Realty LLPPP130000250270110 Mar 202631 Dec 2027—Not yet due0
99 AvenueReliable VenturePR13000025026155 Mar 202631 Dec 2031—Not yet due0
Aatish Central HubIra Earthcon Pvt LtdPM130000250241720 Feb 202630 Jun 2030—Not yet due0
Dwarka - Wing EShree Classic DevelopersPR130000250233912 Feb 202631 Dec 2030—Not yet due0
Aruved Town Phase2Aruved Builders & DevelopersPR130000250214421 Jan 202631 Dec 2030—Not yet due0
Aruved Town Phase 1Aruved Builders & DevelopersPR130000250212220 Jan 202631 Dec 2030—Not yet due0
Deepam ResidencyJanardhan Anantrao VibhutePR130000250211220 Jan 202630 Jun 2028—Not yet due0
ManoramaNaik Nimbalkar InfraPR130000250212620 Jan 202631 Dec 2028—Not yet due0
Kanyaratna Row HousesKanyaratna InfraPR130000250205912 Jan 202631 Dec 2030—Not yet due0
RugvedDurvankur Vastunirmiti Private LimitedPR130000250187726 Dec 202531 Dec 2029—Not yet due0
Hiragan ResidencySarada Landmark Private LimitedPR130000250182417 Dec 202531 Dec 2028—Not yet due0
PetalsDev PropertiesPR130000250179215 Dec 202531 Dec 2029—Not yet due0
Laxmi Shridhar ComplexPhadke Builders and DevelopersPR130000250176112 Dec 202531 Dec 2029—Not yet due0
The Royal AbodeRushikesh DevelopersPR130000250155124 Nov 202530 Apr 2030—Not yet due0
Shree Sai SerenityShree Sai BuildconPM130000250149017 Nov 202531 Dec 2031—Not yet due0
Nehadeep AvenueShriman Builders And DevelopersPR130000250147014 Nov 202531 Aug 2031—Not yet due0
Vyankatesh HeightsVyankatesh Builders SataraPR130000250141710 Nov 202531 Dec 2029—Not yet due0
Samruddhi VastuSamruddhi Builders & DevelopersPR13000025013977 Nov 202531 Dec 2030—Not yet due0
Sai UmeshShirke Constructions Pvt. Ltd.PR130000250135330 Oct 202531 Dec 2030—Not yet due0
Mayuresh ResidencyRahul Bhaskar ShalgarPR130000250132020 Oct 202531 Dec 2029—Not yet due0
Ambika ViharK K DevelopersP5270008101715 Oct 202531 May 2030—Not yet due0
Sanjog NiketanShree Niketan DevelopersPR130000250123315 Oct 202531 May 2028—Not yet due0
The Explorers Club and Country HouseInternational Wellness Residences Private LimitedPM13000025011529 Oct 202531 Dec 2028—Not yet due0
Guru AnganM/S Jadhav Korattil Promoters And DevelopersPR13010125010601 Oct 202531 Dec 2030—Not yet due0
Harmony ApartmentK P AssociatesPM13000025010861 Oct 20257 Dec 2026—Not yet due0
Narayan VishwaKangralkar BuildersPR13000025010231 Oct 202531 Dec 2030—Not yet due0
Deshmukh ElementsSunrise DevelopersPR130000250097526 Sep 202531 Dec 2030—Not yet due0
Vishal EliteVishal Shivajirao JagtapPM130000250097626 Sep 202531 Dec 2029—Not yet due0
Sai Saket ParadiseDream World PropertiesPR130000250085119 Sep 202531 Dec 2030—Not yet due0
Shubhra ResidencyShubhra ResidencyPR130000250082517 Sep 202530 Apr 2028—Not yet due0
Morya ParkMorya Landmark proprietor Pooja Prasad BhattadPM130000250078815 Sep 202530 Apr 2029—Not yet due0
Unity VishwaUnity Buildcon GroupP527000809664 Sep 202531 Dec 2029—Not yet due0
Shiv PrideShiv ConstructionsPM130000250064325 Aug 202531 Dec 2028—Not yet due0
Sindhu PlazzaAmrutjyoti DevelopersPR130000250064025 Aug 202531 Dec 2031—Not yet due0
Lambodar ParkV K G DevelopersPM130000250061420 Aug 202531 May 2029—Not yet due0
Varad Garden Phase IIVarad ConstructionP5270008091211 Aug 202531 Dec 2032—Not yet due0
Abhiashwini ResidencyAbasaheb Jare ConstructionPR13000025005117 Aug 202531 Dec 2029—Not yet due0
Song of the River by Urban MangalamRohan Paper MillsP5270008084617 Jul 202525 Nov 2025—Promised date passed0
Sterling Residency Building C5 And C6Sterling DevelopersPR130101250029216 Jul 202530 Sep 2027—Not yet due0
Balwant HeightsBalwant Properties Pvt LtdP527000807928 Jul 202531 Dec 2030—Not yet due0
Ekdant ResidencyEkdant DevelopersP527000807767 Jul 202525 Aug 2028—Not yet due0
Unicon SquarePradnya Amol KhotlandeP527000807463 Jul 202531 Oct 2027—Not yet due0
Nisarg VillaShree Ganesh Developers And BuildersP5270008071626 Jun 202531 Oct 2029—Not yet due0
Siddhivinayak HeightsSiddhivinayak InfraP5270008071326 Jun 202530 Jun 2027—Not yet due0
Rangsarja EmpireJagtap BuildersP5270008069725 Jun 202531 Dec 2028—Not yet due0
Vardhan GovindVardhan PropertiesP5270008069825 Jun 202531 Dec 2030—Not yet due0
Yashraj ApexSaivarad Infra Private LimitedP5270008069625 Jun 202530 Sep 2028—Not yet due0
Gurukunj ResidencySoham Developers Through Propra Soham Kishor JadhavP5270008065623 Jun 202531 Dec 2028—Not yet due0
Rivera HomesShinde And Shinde AssociatesP5270008062623 Jun 202531 Dec 2028—Not yet due0

Other districts

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Venkatesh Promoters And Builders6 projects
  2. Aditya Developers through Proprietor Kumar Balasaheb Chavan5 projects
  3. ASHWINI BUILDER'S & DEVELOPERS Pvt. Ltd.5 projects
  4. Rajan Namdeo Pore5 projects
  5. Shree Chaitanya Builders5 projects
  6. Swara Construction5 projects
  7. Model Developers And Builders4 projects
  8. M/S. Omkar Developers4 projects
  9. M Sons Builder And Developers4 projects
  10. Shinde Jadhav Builders And Developers4 projects
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology