RERA projects in Lonand (Ct)
2 projects under 2 MahaRERA registrations, registered 2020–2022. None has an extended completion date on record.
Locality
2RERA projects
2Registrations
1Completion still due1 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 1 |
Projects in Lonand (Ct)
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Kalakruti AppartmentAkruti Ventures | P52700047316 | 19 Oct 2022 | 31 Dec 2031 | 31 Dec 2031 | Not yet due | 0 |
| Laxmi Narayan AppartmentAnand Bansilal Pandit | P52700024886 | 9 Mar 2020 | 30 Oct 2021 | 30 Oct 2021 | Promised date passed | 0 |
Other localities in Khandala
Most active promoters
By projects registered here, as named on MahaRERA.
- Akruti Ventures1 project
- Anand Bansilal Pandit1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology