Pargaon, Satara
7 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects2
Registrations3some projects hold several
Completion still due21 past their date
Median extension75 months67% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Pargaon
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Fortune valleyLimra constructions | P52700013042 | 14 Sep 2017 | 31 Dec 2028 | 31 Dec 2028 | Not yet due | 0 |
| My WorldM/S Dada Adinath Projects | P52700010939, P52700011827 | 31 Aug 2017 | 25 Dec 2019 | 24 Jun 2027 | Extended 90 mo | 0 |
Nearby: other localities in Khandala
Most active promoters
- Limra constructions1 project
- M/S Dada Adinath Projects1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology