6 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects113
Registrations114some projects hold several
Completion still due3747 past their date
Median extension4 months36% of registrations extended
Regulatory cases3on 3 projects

6 in 10 registrations run late here

114 MahaRERA registrations in Khandala and the places within it

15 not yet due22 extended, not yet due47 past even the latest date30 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Khandala

113 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Signature VillasNiladri Realty LLPDue Sep 2029——
Tajcitrus ParkFiltrum Infrastructure Private LimitedDue Dec 2031——
Akshay ParkAkshay Civil Engineers And ContractorsDue Jan 2031, extended 4 mo——
Menlo FrontyardBlue Ladder Estates Private LimitedCompleted——
PetalsDev PropertiesDue Apr 2030, extended 4 mo——
All 113 projects →
Khandala market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Alliance Vanashree Ventures2 projects
  2. Amalfi Enterprise2 projects
  3. Blue Ladder Estates Pvt Ltd2 projects
  4. Filtrum Infrastructure Pvt Ltd2 projects
  5. Sagar Mahadev Jarad2 projects
  6. Shriram Developers2 projects
  7. Sterling Developers2 projects
  8. Ab Reality1 project
  9. Akruti Ventures1 project
  10. Akshay Civil Engineers And Contractors1 project

Khandala, in questions

How many projects in Khandala run late?

6 in 10 MahaRERA registrations (69 of 114): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Khandala by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology