Skip to content
Deedo home
Menu

RERA projects in Mahabaleshwar

6 projects under 9 MahaRERA registrations, registered 2017–2025. 13% have a completion date extended beyond the one promised.

Taluka
6RERA projects
9Registrationssome projects hold several
6Completion still due2 past their completion date
18 monthsMedian extension beyond promised date13% of registrations extended
1Regulatory caseson 1 project
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20181
20193
20200
20210
20221
20230
20240
20252

Projects in Mahabaleshwar

6 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Mango Lakefront TapolaMv Tapola Private LimitedP52700079010, P5270007906931 Jan 202531 Oct 2034—Not yet due0
Nivaan HillsVishal Ashok ChugeraP5270004565026 May 202230 Jun 2027—Not yet due1
RutuGandh MahabaleshwarHi-Tek Vyas Developers LLPP52700023105, P52700023106, P527000232512 Dec 201930 Jun 2028—Not yet due0
Strawberry HillsNavnath DevelopersP5270001532415 Feb 201820 Jun 202120 Dec 2022Extended 18 mo0
Windsor ParkKumar BuildersP5270000715617 Aug 201730 Dec 2023—Promised date passed0
Maharaja ValleyP52700000243————0

Other talukas in Satara

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Hi-Tek Vyas Developers LLP1 project
  2. Kumar Builders1 project
  3. Mv Tapola Private Limited1 project
  4. Navnath Developers1 project
  5. Vishal Ashok Chugera1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology