RERA projects in Kolki (Ct)

29 projects under 30 MahaRERA registrations, registered 2017–2025. 7% have a completion date extended beyond the one promised.

29RERA projects
30Registrationssome projects hold several
12Completion still due18 past their completion date
52 monthsMedian extension beyond promised date7% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20178
20182
20192
20200
20216
20222
20232
20241
20257

Projects in Kolki (Ct)

29 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Lambodar ParkV K G DevelopersPM130000250061420 Aug 202531 May 2029—Not yet due0
Vitthal PrideAgastya PropertiesP5270008064523 Jun 202531 Mar 2028—Not yet due0
Nd ParkNd GroupP5270008034926 May 202531 Dec 2027—Not yet due0
Trimurti HeightsChandrakant Sadhu PakhaleP5270008013430 Apr 202531 Mar 2027—Not yet due0
Mayuresh ParkShri Balaji DevelopersP5270007978026 Mar 202531 Dec 2030—Not yet due0
Ramsrushti ApartmentM/S Ram Group, JadhavwadiP5270007921317 Feb 20251 Nov 2029—Not yet due0
Govind ParkVikram Sanjay NimbalkarP52700054856, PM130000250109315 Feb 202427 Mar 2030—Not yet due0
Kalpataru TowersN D DevelopersP5270005403927 Dec 20231 Sep 2026—Promised date passed0
Sunshine Landmark Phase IIPSK GroupP5270004859110 Jan 20231 Apr 2025—Promised date passed0
J.k.classicJ K AssociatesP5270004834426 Dec 202231 Dec 2027—Not yet due0
Sai TowersAnandrao Haribhau KalukheP527000470973 Oct 202230 Jun 2025—Promised date passed0
Nd VillaNd DevelopersP5270003214014 Dec 202131 Dec 2024—Promised date passed0
Indus LandmarkIndus PromotersP5270003191022 Nov 202131 Dec 2027—Not yet due0
Vasundhara GardenVasundhara GardenP5270003054530 Aug 202131 Mar 202431 Dec 2026Extended 33 mo0
Sunshine LandmarkSunshine LandmarkP527000302045 Aug 202131 Dec 2023—Promised date passed0
Govind TowerSanjeev Vijaysinh Naik NimbalkarP5270002871425 Mar 202130 Sep 2025—Promised date passed0
Indus RoyalRajiv Sureshrao Naik NimbalkarP5270002869625 Mar 202127 Sep 2024—Promised date passed0
Vasundhara ParkRohit Vasantrao GhanwatP527000214633 Jul 201930 Mar 2023—Promised date passed0
Swarajya PrimeM/S - Swarajya GroupP5270002079510 May 201930 Dec 202131 Oct 2027Extended 70 mo0
J K PrideGeeta Narayan JethwaniP527000179883 Oct 20181 Jul 2019—Promised date passed0
Shreeram Towers CShreeram Promoters And DevelopersP5270001707711 Jul 201830 Dec 2021—Promised date passed0
Varad Vinayak ResidencyVaradvinayak Builders and DevelopersP5270000963522 Aug 201713 May 2023—Promised date passed0
Trimurti Classic DChandrakant Sadhu PakhaleP5270000873519 Aug 20171 Mar 2019—Promised date passed0
Shreeram towers BShreeram Promoters And DevelopersP5270000841118 Aug 201730 Jun 2018—Promised date passed0
Shreeram Towers AShreeram Promoters and DevelopersP5270000751717 Aug 201730 Jun 2018—Promised date passed0
Indus ClassicIndus DevelopersP527000031234 Aug 201731 Mar 2018—Promised date passed0
SwapnapurtiAshwamegh DevelopersP527000026992 Aug 201731 Mar 2019—Promised date passed0
Vasundhara PrimeVasundhara PrimeP5270000204131 Jul 201731 Mar 2018—Promised date passed0
Ayodhya ParkRam GroupP5270000144028 Jul 201730 Dec 2021—Promised date passed0

Other localities in Phaltan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Shreeram Promoters and Developers3 projects
  2. Chandrakant Sadhu Pakhale2 projects
  3. Agastya Properties1 project
  4. Anandrao Haribhau Kalukhe1 project
  5. Ashwamegh Developers1 project
  6. Geeta Narayan Jethwani1 project
  7. Indus Developers1 project
  8. Indus Promoters1 project
  9. J K Associates1 project
  10. M/S Ram Group, Jadhavwadi1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology