RERA projects in Khanapur

2 projects under 2 MahaRERA registrations, registered 2020–2021. 50% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
1Completion still due1 past their completion date
4 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
8Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20201
20211

Projects in Khanapur

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Wai SamikSumedha Infracon ProjectsP527000320733 Dec 202113 Oct 202413 Oct 2024Promised date passed0
Sakshi Vishwa Phase IIM/S Sakshi Nine Blossom DevelopersP5270002612020 Aug 202030 Jun 202730 Oct 2027Extended 4 mo0

Other localities in Wai

Most active promoters

By projects registered here, as named on MahaRERA.

  1. M/S Sakshi Nine Blossom Developers1 project
  2. Sumedha Infracon Projects1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology