Satara (M Cl), Satara
Deedo IDDL-SAT-SATARA-42 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects16
Registrations16
Completion still due313 past their date
Median extension11 months19% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
16 MahaRERA registrations in Satara (M Cl)
1 not yet due2 extended, not yet due13 past even the latest date
Extended registrations moved their completion date by a median of 11 months.
Projects in Satara (M Cl)
16 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Laxmi Shridhar ComplexPhadke Builders and Developers | Due Dec 2029 | — | — |
| Shivrudra PrideAsp Gruh Private Limited | Due Mar 2028, extended 4 mo | — | 29% |
| Shree Gulab PushpM M Power & Infrastructure | 3 yrs 10 mo late | — | 0% |
| Shubham Sankul B wingJaymorya Builders | 1 yr 10 mo late | — | 0% |
| Datta Vihar ApartmentKangralkar Ventures | 3 yrs 5 mo late | — | 100% |
| AranyaPrashant Mohan Barge | 4 yrs 4 mo late | — | 100% |
| Vedant ResidencyAtharv Builders And Developers | 1 mo late | — | 0% |
| Chavan Chorage ComplexTarachand Lombaji Tapase | Due Dec 2029, extended 6 yrs 3 mo | — | 0% |
| Dhanashri HeightsSapana Ganesh Shinde | 2 yrs 10 mo late | — | 94% |
| Anvi PrideAnay Developers | 2 yrs 10 mo late | — | 0% |
| ShubhamkarotiClassic Hestia Developers | 1 yr 7 mo late | — | — |
| Jp ResidencyJp Builders & Developers | 4 yrs 5 mo late | — | 0% |
| Dattakrupa Shopping ComplexTarachnad Limbaji Tapase | 8 yrs 4 mo late | — | 100% |
| Mahalaxmi SankulMahalaxmi Developers | 7 yrs 10 mo late | — | 26% |
| Siddheshwar TowerS S Promoters And Developers | 5 yrs 9 mo late | — | 14% |
| Chaitanya LaxmiVyankatesh Developers | 8 yrs late | — | 18% |
Nearby: other localities in Satara
Most active promoters
- Anay Developers1 project
- Asp Gruh Private Limited1 project
- Atharv Builders And Developers1 project
- Classic Hestia Developers1 project
- Jaymorya Builders1 project
- Jp Builders & Developers1 project
- Kangralkar Ventures1 project
- Mahalaxmi Developers1 project
- M M Power & Infrastructure1 project
- Phadke Builders and Developers1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology