RERA projects in Khindwadi

5 projects under 5 MahaRERA registrations, registered 2017–2023. 40% have a completion date extended beyond the one promised.

Locality
5RERA projects
5Registrations
2Completion still due3 past their completion date
4 monthsMedian extension beyond promised date40% of registrations extended
0Regulatory casesnone on MahaRERA's lists
6Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20180
20190
20201
20211
20221
20231

Projects in Khindwadi

5 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Swarnamangal ResidencyRajmangal BuildersP527000485446 Jan 202331 Dec 202730 Apr 2028Extended 4 mo0
Keshav SrushtiAbhishek Subhash NikamP5270004741227 Oct 202231 Dec 203030 Apr 2031Extended 4 mo0
Gajanan NagariGajanan Keshavrao UttekarP5270003044725 Aug 202131 Aug 202431 Aug 2024Promised date passed0
Sai DarshanAmol Nanaso GhadageP527000252965 Apr 202030 Oct 202330 Oct 2023Promised date passed0
Dream PrideDream World Construction LLPP5270001415810 Nov 201730 Nov 201930 Nov 2019Promised date passed0

Other localities in Satara

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Abhishek Subhash Nikam1 project
  2. Amol Nanaso Ghadage1 project
  3. Dream World Construction LLP1 project
  4. Gajanan Keshavrao Uttekar1 project
  5. Rajmangal Builders1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology