RERA projects in Khindwadi
5 projects under 5 MahaRERA registrations, registered 2017–2023. 40% have a completion date extended beyond the one promised.
Locality
5RERA projects
5Registrations
2Completion still due3 past their completion date
4 monthsMedian extension beyond promised date40% of registrations extended
0Regulatory casesnone on MahaRERA's lists
6Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 1 |
| 2021 | 1 |
| 2022 | 1 |
| 2023 | 1 |
Projects in Khindwadi
5 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Swarnamangal ResidencyRajmangal Builders | P52700048544 | 6 Jan 2023 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Keshav SrushtiAbhishek Subhash Nikam | P52700047412 | 27 Oct 2022 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Gajanan NagariGajanan Keshavrao Uttekar | P52700030447 | 25 Aug 2021 | 31 Aug 2024 | 31 Aug 2024 | Promised date passed | 0 |
| Sai DarshanAmol Nanaso Ghadage | P52700025296 | 5 Apr 2020 | 30 Oct 2023 | 30 Oct 2023 | Promised date passed | 0 |
| Dream PrideDream World Construction LLP | P52700014158 | 10 Nov 2017 | 30 Nov 2019 | 30 Nov 2019 | Promised date passed | 0 |
Other localities in Satara
Most active promoters
By projects registered here, as named on MahaRERA.
- Abhishek Subhash Nikam1 project
- Amol Nanaso Ghadage1 project
- Dream World Construction LLP1 project
- Gajanan Keshavrao Uttekar1 project
- Rajmangal Builders1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology