RERA projects in Vanvaswadi
19 projects under 19 MahaRERA registrations, registered 2017–2026. 11% have a completion date extended beyond the one promised.
19RERA projects
19Registrations
10Completion still due9 past their completion date
32 monthsMedian extension beyond promised date11% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 4 |
| 2018 | 1 |
| 2019 | 1 |
| 2020 | 1 |
| 2021 | 1 |
| 2022 | 3 |
| 2023 | 3 |
| 2024 | 0 |
| 2025 | 2 |
| 2026 | 3 |
Projects in Vanvaswadi
19 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Mangalmurti ComplexSankalp Developers | PM1300002601996 | 22 Sep 2026 | 31 Dec 2032 | — | Not yet due | 0 |
| Saavi The Heart Of VikasnagarSaavi The Heart Of Vikasnagar | PR1300002600103 | 15 Apr 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Narayan AshwiniAbasaheb Jare Construction | PR1300002502897 | 18 Mar 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Abhiashwini ResidencyAbasaheb Jare Construction | PR1300002500511 | 7 Aug 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Vishwakarma ResidencyVishwakarma Construction | P52700079456 | 6 Mar 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Spruhaashwini ResidencyASHWINI BUILDER'S & DEVELOPERS Pvt. Ltd. | P52700051489 | 23 Jun 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Naik PlazaClassic Constructions | P52700049580 | 15 Feb 2023 | 16 Nov 2027 | — | Not yet due | 0 |
| Kartikeya VillaKartikeya Developers | P52700048399 | 3 Jan 2023 | 15 Aug 2025 | — | Promised date passed | 0 |
| Herambh ResidencySankalp Developers | P52700046947 | 26 Sep 2022 | 31 Dec 2027 | — | Not yet due | 0 |
| Madhav Pushp Building B 2Bhoomata Builders And Developers | P52700046256 | 20 Jun 2022 | 1 Jun 2027 | — | Not yet due | 0 |
| Tirupati NiwasRamesh Anil Ubale | P52700032851 | 2 Feb 2022 | 30 Oct 2026 | — | Not yet due | 0 |
| NeelayaAvani Infrastructure | P52700032202 | 15 Dec 2021 | 31 Dec 2025 | — | Promised date passed | 0 |
| LataashwiniASHWINI BUILDER'S & DEVELOPERS Pvt. Ltd. | P52700025746 | 9 Jul 2020 | 30 Sep 2024 | — | Promised date passed | 0 |
| Shivaraj ResidencyRanjit Dinkar Shinde | P52700022573 | 7 Oct 2019 | 30 Dec 2023 | — | Promised date passed | 0 |
| Reliable HeightsReliable Builders | P52700016158 | 20 Apr 2018 | 16 Oct 2019 | 15 Oct 2021 | Extended 24 mo | 0 |
| KartikiashwiniASHWINI BUILDER'S & DEVELOPERS Pvt. Ltd. | P52700014192 | 14 Nov 2017 | 30 Dec 2022 | — | Promised date passed | 0 |
| Sonaashwini ResidencyASHWINI BUILDER'S & DEVELOPERS Pvt. Ltd. | P52700011287 | 31 Aug 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Unique PlazaUnique Properties | P52700011400 | 31 Aug 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Reliable HeightsReliable Realities | P52700004651 | 9 Aug 2017 | 31 Oct 2018 | 28 Feb 2022 | Extended 40 mo | 0 |
Other localities in Satara
- Satara99 projects
- Karanje Tarf Satara (Ct)95 projects
- Godoli (Ct)61 projects
- Kodoli (Ct)41 projects
- Khed (Ct)29 projects
- Satara (M Cl)16 projects
- Sadarbazar13 projects
- Kondhave10 projects
- Sadarbazar (Ct)9 projects
- Pirwadi8 projects
- Saidapur6 projects
- Khindwadi5 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- ASHWINI BUILDER'S & DEVELOPERS Pvt. Ltd.4 projects
- Abasaheb Jare Construction2 projects
- Sankalp Developers2 projects
- Avani Infrastructure1 project
- Bhoomata Builders And Developers1 project
- Classic Constructions1 project
- Kartikeya Developers1 project
- Ramesh Anil Ubale1 project
- Ranjit Dinkar Shinde1 project
- Reliable Builders1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology