Satara
Deedo IDDL-SAT-SATARA-39 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects124
Registrations125some projects hold several
Completion still due4382 past their date
Median extension4 months35% of registrations extended
Regulatory cases3on 3 projects
9 in 10 registrations run late here
125 MahaRERA registrations in Satara
9 not yet due34 extended, not yet due82 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Satara
124 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Skyline ResidencySkyline Builder And Developers | Due Mar 2033 | — | — |
| Moon Light TowerRaj Builders | Due Apr 2031, extended 4 mo | — | — |
| RugvedDurvankur Vastunirmiti Private Limited | Due Apr 2030, extended 4 mo | — | — |
| The Royal AbodeRushikesh Developers | Due Aug 2030, extended 4 mo | — | — |
| Vyankatesh HeightsVyankatesh Builders Satara | Due Dec 2029 | — | — |
Nearby: other villages in Satara
Most active promoters
- Shree Chaitanya Builders5 projects
- Model Developers And Builders4 projects
- Shinde Jadhav Builders And Developers3 projects
- Abhishek Nandkumar Phadke2 projects
- Aditya Developers Through Proprietor Kumar Balasaheb Chavan2 projects
- Kachhi Properties2 projects
- Nandkumar Vinayak Phadke2 projects
- Niketan Construction2 projects
- Rajendra Madhukar Chorage2 projects
- Abhishek Radheshyam Bhandari1 project
Satara, in questions
How many projects in Satara run late?
9 in 10 MahaRERA registrations (116 of 125): their completion date was extended or has passed, data through 6 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Satara by Deedo. Medians on fewer than 3 deeds are not shown.
Data through6 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology