RERA projects in Kuroshi

1 project under 1 MahaRERA registration, registered 2022–2022. 100% have a completion date extended beyond the one promised.

Locality
1RERA projects
1Registrations
1Completion still due0 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
1Regulatory caseson 1 project
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20221

Projects in Kuroshi

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Nivaan HillsVishal Ashok ChugeraP5270004565026 May 202230 Jun 202730 Oct 2027Extended 4 mo1

Other localities in Mahabaleshwar

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Vishal Ashok Chugera1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology