RERA projects in Ahire
1 project under 2 MahaRERA registrations, registered 2025–2025. 100% have a completion date extended beyond the one promised.
Locality
1RERA projects
2Registrationssome projects hold several
2Completion still due0 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
90Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2025 | 2 |
Projects in Ahire
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Mango Lakefront TapolaMv Tapola Private Limited | P52700079010, P52700079069 | 31 Jan 2025 | 31 Oct 2034 | 28 Feb 2035 | Extended 4 mo | 0 |
Other localities in Mahabaleshwar
Most active promoters
By projects registered here, as named on MahaRERA.
- Mv Tapola Private Limited1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology