Saidapur (Ct), Satara

Deedo IDDL-SAT-SAIDAPUR-2

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects19
Registrations19
Completion still due613 past their date
Median extension4 months32% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

19 MahaRERA registrations in Saidapur (Ct)

2 not yet due4 extended, not yet due13 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Saidapur (Ct)

19 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
silver valleyDevashree Garden LLPDue Aug 2030——
Aruved Town Phase2Aruved Builders & DevelopersDue Apr 2031, extended 4 mo——
Aruved Town Phase 1Aruved Builders & DevelopersDue Apr 2031, extended 4 mo——
Kanyaratna Row HousesKanyaratna InfraDue Apr 2031, extended 4 mo——
Gurudarshan Phase IIGurudatta Builders And DevelopersDue Feb 2028, extended 4 mo—6%
All 19 projects →
Saidapur (Ct) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Aruved Builders & Developers2 projects
  2. Gurudatta Builders And Developers2 projects
  3. Kanyaratna Infra2 projects
  4. Nilesh Vitthalrao Patil2 projects
  5. Satvashil Dnyandev Kadam2 projects
  6. Abhijit Shankarrao Jadhav1 project
  7. Deepak Lalasaheb Pawar1 project
  8. Desai And Patil Builders And Developers1 project
  9. Devashree Garden LLP1 project
  10. Disha Developers1 project

Saidapur (Ct), in questions

How many projects in Saidapur (Ct) run late?

9 in 10 MahaRERA registrations (17 of 19): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Saidapur (Ct) by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology