Jakhinwadi, Satara

3 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects3
Registrations3
Completion still due21 past their date
Median extension4 months33% of registrations extended
Regulatory cases0none on MahaRERA's lists
Jakhinwadi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

7 in 10 registrations run late here

3 MahaRERA registrations in Jakhinwadi

1 not yet due1 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Jakhinwadi

3 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
D S HeritageD S DevelopersDue Apr 2028, extended 4 mo—0%
D S ComplexD S DevelopersDue Dec 2026—0%
Shriram PrideSaraswati Builders And Developers5 yrs 9 mo late—0%

Most active promoters

  1. D S Developers2 projects
  2. Saraswati Builders And Developers1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology