RERA projects in Malkapur (Np)
64 projects under 65 MahaRERA registrations, registered 2017–2026. 11% have a completion date extended beyond the one promised.
64RERA projects
65Registrationssome projects hold several
27Completion still due38 past their completion date
25 monthsMedian extension beyond promised date11% of registrations extended
1Regulatory caseson 1 project
10Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 4 |
| 2018 | 5 |
| 2019 | 13 |
| 2020 | 5 |
| 2021 | 3 |
| 2022 | 6 |
| 2023 | 5 |
| 2024 | 8 |
| 2025 | 8 |
| 2026 | 8 |
Projects in Malkapur (Np)
64 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| AnandnagarAnil Anandrao Shingan, Vidya Vishal Ingawale, Suman Anandrao Shingan | PR1300002601959 | 17 Sep 2026 | 1 May 2029 | — | Not yet due | 0 |
| Panchratna CrystalShree Panchratna Group | PR1300002601790 | 4 Sep 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Rohan Heights Phase IIIRohan Builders | PR1300002601684 | 27 Aug 2026 | 31 Dec 2031 | — | Not yet due | 0 |
| Vrundavan CityKalyani Infra | PM1300002601449, PM1300002601507 | 7 Aug 2026 | 1 Jun 2030 | — | Not yet due | 0 |
| Anuraj Arcaed Tower DAnuraj Construction | PR1300002601292 | 23 Jul 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Dwarka CityHeramb Infra | PM1300002600721 | 10 Jun 2026 | 31 Dec 2031 | — | Not yet due | 0 |
| Aatish Central HubIra Earthcon Pvt Ltd | PM1300002502417 | 20 Feb 2026 | 30 Jun 2030 | — | Not yet due | 0 |
| Harmony ApartmentK P Associates | PM1300002501086 | 1 Oct 2025 | 7 Dec 2026 | — | Not yet due | 0 |
| Vishal EliteVishal Shivajirao Jagtap | PM1300002500976 | 26 Sep 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Devgiri Row BungalowsPerfect Builders And Developers | P52700080506 | 11 Jun 2025 | 15 Apr 2026 | — | Promised date passed | 0 |
| Kst Central ParkKst Constructions | P52700080301 | 19 May 2025 | 7 Dec 2030 | — | Not yet due | 0 |
| Rau Gold CoastShreem Multicon Private Limited | P52700080275 | 15 May 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Vrundavan City Phase 3Kalyani Associates | P52700079899 | 28 Mar 2025 | 1 Feb 2028 | — | Not yet due | 0 |
| Smaark oneDevashree Garden LLP | P52700079564 | 12 Mar 2025 | 10 Jan 2028 | — | Not yet due | 0 |
| Sai ResidencyShri Sai Developers | P52700078989 | 28 Jan 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Silver SpringsJanardhan Pandurang Jadhav | P52700078333 | 4 Dec 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| MangalmurtiVijaykumar Nivrutti Patil | P52700056371 | 31 May 2024 | 31 Jan 2029 | — | Not yet due | 0 |
| Shat Taraka HeightsUltrasindhu Developers | P52700056344 | 29 May 2024 | 31 Dec 2030 | — | Not yet due | 0 |
| Anita HeightsPriyanka Vikram Chavan | P52700056194 | 16 May 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Panchratna ClassicPanchratna Classic | P52700055147 | 4 Mar 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| ShivanuShivanu Constructions Private Limited | P52700054875 | 15 Feb 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Vrundavan City Phase-2aKalyani Associates | P52700054596 | 31 Jan 2024 | 1 May 2026 | — | Promised date passed | 0 |
| OrionSai Sharda Devlopers | P52700054284 | 15 Jan 2024 | 1 Dec 2025 | — | Promised date passed | 0 |
| Vishal PrideShivaji Shankar Jagtap | P52700050670 | 28 Apr 2023 | 1 Jan 2025 | — | Promised date passed | 0 |
| Shubhashree IconShubhashree Infrastructure | P52700050500 | 17 Apr 2023 | 5 Jan 2025 | — | Promised date passed | 0 |
| AurumYes Infrabuild Private Limited | P52700049941 | 6 Mar 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| J P PrideJ P Associates | P52700049882 | 6 Mar 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Shivsamruddhi TowersShivsrushti Buildcon | P52700048763 | 17 Jan 2023 | 15 Dec 2026 | — | Not yet due | 0 |
| J P SquareJ P Square | P52700047006 | 26 Sep 2022 | 30 Sep 2025 | — | Promised date passed | 0 |
| Panchratna PremiumPanchratna Premium | P52700046459 | 4 Aug 2022 | 13 May 2025 | — | Promised date passed | 0 |
| The SkyDreems Builder | P52700034997 | 28 Apr 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Srushti SankulVishal Shivajirao Jagtap | P52700033182 | 9 Feb 2022 | 31 Dec 2023 | — | Promised date passed | 0 |
| HerambASIAHeramb developers | P52700032922 | 2 Feb 2022 | 25 Nov 2022 | 30 Dec 2024 | Extended 25 mo | 0 |
| Indumati ResidenceSaidatta Builders And Developers | P52700032602 | 14 Jan 2022 | 3 Nov 2024 | — | Promised date passed | 1 |
| Vrundavan City - 2Kalyani Associates | P52700031423 | 23 Oct 2021 | 3 Mar 2024 | — | Promised date passed | 0 |
| Dream VillaKrishna Assocaites | P52700028858 | 5 Apr 2021 | 30 Jun 2024 | — | Promised date passed | 0 |
| Panchratna EmpirePanchratna Infra | P52700027899 | 14 Jan 2021 | 30 Jun 2023 | — | Promised date passed | 0 |
| Square CastleCredence Properties | P52700025373 | 13 May 2020 | 31 Dec 2027 | — | Not yet due | 0 |
| Siddhivinayak SankulShivsai Developers | P52700025059 | 18 Mar 2020 | 4 Jan 2022 | — | Promised date passed | 0 |
| Tukai HeightsChandrashekhar Tukaram Vibhute | P52700024702 | 28 Feb 2020 | 30 Dec 2024 | 31 Dec 2029 | Extended 60 mo | 0 |
| Laxmi ResidencyHrd Builders & Developers | P52700023732 | 3 Jan 2020 | 1 Feb 2024 | 31 Oct 2025 | Extended 20 mo | 0 |
| Shri Ballaleshwar SankulBhimashankar Irrapa Mavoor | P52700023702 | 2 Jan 2020 | 30 Jun 2022 | — | Promised date passed | 0 |
| Tanisha TowerShivaji Shankar Jagtap | P52700023247 | 9 Dec 2019 | 30 Mar 2022 | — | Promised date passed | 0 |
| Anuraj ArcadeAnuraj Construction | P52700023029 | 14 Nov 2019 | 30 Dec 2024 | — | Promised date passed | 0 |
| Omkar ResidencyS P Developers | P52700022572 | 7 Oct 2019 | 31 Jul 2022 | — | Promised date passed | 0 |
| Saikrupa HeightsVikram Sanjay Pol | P52700022390 | 19 Sep 2019 | 15 Apr 2022 | 31 Mar 2023 | Extended 11 mo | 0 |
| Siddhivinayak HeightsNirmiti Infraa | P52700021933 | 8 Aug 2019 | 30 Apr 2022 | — | Promised date passed | 0 |
| Vrundavan CityKalyani Buildcon | P52700021161 | 14 Jun 2019 | 11 May 2025 | — | Promised date passed | 0 |
| Kst AanandlaxmiSarjerao Anandrao Patil | P52700021105 | 31 May 2019 | 12 Sep 2023 | — | Promised date passed | 0 |
| Shivsai ResidencyAmit Shantaram Patil | P52700020790 | 9 May 2019 | 1 Apr 2022 | — | Promised date passed | 0 |
| Gargi ResidencySagar Dilip Jadhav | P52700020743 | 8 May 2019 | 7 Nov 2021 | — | Promised date passed | 0 |
| EmraldSaj Realty | P52700019725 | 5 Mar 2019 | 19 Feb 2023 | — | Promised date passed | 0 |
| Sai PrestigeDilip Nivruti Jadhav | P52700019752 | 5 Mar 2019 | 30 Dec 2023 | — | Promised date passed | 0 |
| Ashok DeepDreamWorld Builders And Developers | P52700019543 | 8 Feb 2019 | 10 Feb 2023 | 10 Feb 2024 | Extended 12 mo | 0 |
| Unnati ApartmentAjit Construction And Developers | P52700019446 | 30 Jan 2019 | 12 Nov 2021 | 31 Mar 2025 | Extended 40 mo | 0 |
| Galaxy HeightsVikas Narayan Deokar | P52700019070 | 28 Dec 2018 | 30 Dec 2020 | 31 Dec 2026 | Extended 72 mo | 0 |
| Damayanti PlazaYadav - Patil Developers | P52700017135 | 16 Jul 2018 | 25 Mar 2022 | — | Promised date passed | 0 |
| Vardhan PlazaBalasaheb Bapu Wadkar | P52700015971 | 10 Apr 2018 | 30 Dec 2022 | — | Promised date passed | 0 |
| Exotica-IIDeepak Shankarrao Patil | P52700014899 | 11 Jan 2018 | 30 Sep 2020 | — | Promised date passed | 0 |
| Panchratna ParkHindustan Construction Builders & Developers | P52700014829 | 8 Jan 2018 | 31 Dec 2018 | — | Promised date passed | 0 |
| Vedantika PrideVedant Infra | P52700014415 | 29 Nov 2017 | 30 Jan 2022 | — | Promised date passed | 0 |
| The Nest RealtyThe Nest Realty | P52700013745 | 25 Oct 2017 | 30 Mar 2021 | — | Promised date passed | 0 |
| Heramb ResidencyShri Sai Developers | P52700012960 | 7 Sep 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Kst PlanetKst Constructions | P52700003925 | 7 Aug 2017 | 30 Jun 2023 | 30 Jun 2023 | Promised date passed | 0 |
Other localities in Karad
- Karad (M Cl)39 projects
- Saidapur (Ct)19 projects
- Karad (Rural) (Ct)5 projects
- Goleshwar4 projects
- Mundhe4 projects
- Umbraj4 projects
- Jakhinwadi3 projects
- Koyanavasahat3 projects
- Gote2 projects
- Parle2 projects
- Vanvadi (Sadashivgad)2 projects
- Khodshi1 project
Most active promoters
By projects registered here, as named on MahaRERA.
- Kalyani Associates3 projects
- Anuraj Construction2 projects
- Kst Constructions2 projects
- Shivaji Shankar Jagtap2 projects
- Shri Sai Developers2 projects
- Vishal Shivajirao Jagtap2 projects
- Ajit Construction And Developers1 project
- Amit Shantaram Patil1 project
- Anil Anandrao Shingan, Vidya Vishal Ingawale, Suman Anandrao Shingan1 project
- Balasaheb Bapu Wadkar1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology