Gote, Satara
5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects2
Registrations2
Completion still due02 past their date
Median extension25 months50% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
2 MahaRERA registrations in Gote
2 past even the latest date
Extended registrations moved their completion date by a median of 25 months.
Projects in Gote
2 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Satyajeet VillaSatyajeet Villa | 3 yrs 10 mo late | — | 100% |
| Vedantika ResidencyVedantika Infra | 4 yrs 7 mo late | — | 50% |
Nearby: other localities in Karad
Most active promoters
- Satyajeet Villa1 project
- Vedantika Infra1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology