10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4
Registrations4
Completion still due31 past their date
Median extension4 months75% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

4 MahaRERA registrations in Mundhe

3 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Mundhe

4 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Keyur ResidencyAmit Shantaram PatilDue Apr 2032, extended 4 mo——
Vardhan GovindVardhan PropertiesDue Apr 2031, extended 4 mo——
Shriram City Wing BVijaykumar Ramesh DhumalDue Apr 2028, extended 4 mo——
Shivkrupa HightsS K P Constucton5 yrs late——
Mundhe market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Amit Shantaram Patil1 project
  2. S K P Constucton1 project
  3. Vardhan Properties1 project
  4. Vijaykumar Ramesh Dhumal1 project

Mundhe, in questions

How many projects in Mundhe run late?

10 in 10 MahaRERA registrations (4 of 4): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Mundhe by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology