Deedo IDDL-SAT-MUNDHE10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects4
Registrations4
Completion still due31 past their date
Median extension4 months75% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
4 MahaRERA registrations in Mundhe
3 extended, not yet due1 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Mundhe
4 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Keyur ResidencyAmit Shantaram Patil | Due Apr 2032, extended 4 mo | — | — |
| Vardhan GovindVardhan Properties | Due Apr 2031, extended 4 mo | — | — |
| Shriram City Wing BVijaykumar Ramesh Dhumal | Due Apr 2028, extended 4 mo | — | — |
| Shivkrupa HightsS K P Constucton | 5 yrs late | — | — |
Nearby: other villages in Karad
Most active promoters
- Amit Shantaram Patil1 project
- S K P Constucton1 project
- Vardhan Properties1 project
- Vijaykumar Ramesh Dhumal1 project
Mundhe, in questions
How many projects in Mundhe run late?
10 in 10 MahaRERA registrations (4 of 4): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Mundhe by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology