RERA projects in Dabewadi

3 projects under 3 MahaRERA registrations, registered 2018–2023. None has an extended completion date on record.

3RERA projects
3Registrations
2Completion still due1 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20181
20190
20200
20210
20221
20231

Projects in Dabewadi

3 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Padmavati ResidencyPrasanna Pradiprao ShindeP527000493607 Feb 202313 Nov 2027—Not yet due0
Baba ResidencySalim ShaikhP527000332129 Feb 202231 Dec 2028—Not yet due0
Arzoo NagarArzoo Swabhiman Nagarik Sahkari Gruhrachana Sanstha MaryaditP5270001821515 Oct 201831 Jan 2022—Promised date passed0

Other localities in Satara

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Arzoo Swabhiman Nagarik Sahkari Gruhrachana Sanstha Maryadit1 project
  2. Prasanna Pradiprao Shinde1 project
  3. Salim Shaikh1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology