RERA projects in Nune

1 project under 1 MahaRERA registration, registered 2017–2017. 100% have a completion date extended beyond the one promised.

Locality
1RERA projects
1Registrations
0Completion still due1 past their completion date
12 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171

Projects in Nune

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Heramb VastuHeramb Builders & DevelopersP5270001065631 Aug 201730 Dec 202030 Dec 2021Extended 12 mo0

Other localities in Satara

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Heramb Builders & Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology