RERA projects in Bholi

1 project under 1 MahaRERA registration, registered 2021–2021. 100% have a completion date extended beyond the one promised.

1RERA projects
1Registrations
0Completion still due1 past their completion date
24 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20211

Projects in Bholi

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
KalpvrkshaDharmaji Maruti BhosaleP5270003073913 Sep 202131 Dec 202131 Dec 2023Extended 24 mo0

Other localities in Khandala

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Dharmaji Maruti Bhosale1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology