Patan (Ct), Satara
Deedo IDDL-SAT-PATAN-28 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects4
Registrations4
Completion still due22 past their date
Median extension6 months75% of registrations extended
Regulatory cases0none on MahaRERA's lists
8 in 10 registrations run late here
4 MahaRERA registrations in Patan (Ct)
1 not yet due1 extended, not yet due2 past even the latest date
Extended registrations moved their completion date by a median of 6 months.
Projects in Patan (Ct)
4 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Ranjit PlazaSkyline Developers | Due Apr 2031, extended 4 mo | — | — |
| Patan PrideSa Associates | Due Mar 2027 | — | 4% |
| Aditi AarambhVijay Rajaram Pawar | Completed, extended 7 mo | — | — |
| Sky VillasAgreen Infrastructure Pvt Ltd | Completed, extended 2 yrs 6 mo | — | 15% |
Nearby: other municipal areas in Patan
Most active promoters
- Agreen Infrastructure Pvt Ltd1 project
- Sa Associates1 project
- Skyline Developers1 project
- Vijay Rajaram Pawar1 project
Patan (Ct), in questions
How many projects in Patan (Ct) run late?
8 in 10 MahaRERA registrations (3 of 4): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Patan (Ct) by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology