RERA projects in Mandrulkole
2 projects under 2 MahaRERA registrations, registered 2020–2024. None has an extended completion date on record.
2RERA projects
2Registrations
1Completion still due1 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 1 |
Projects in Mandrulkole
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Bhaskar PlazzaSharad Bhaskar Dheb | P52700055394 | 22 Mar 2024 | 28 Sep 2028 | — | Not yet due | 0 |
| Nirman SankulNirman Associates | P52700027298 | 1 Dec 2020 | 30 Jun 2024 | — | Promised date passed | 0 |
Other localities in Patan
- Patan (Ct)4 projects
- Malharpeth1 project
- Nisare1 project
Most active promoters
By projects registered here, as named on MahaRERA.
- Nirman Associates1 project
- Sharad Bhaskar Dheb1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology