9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects791in 25 localities
Registrations796some projects hold several
Completion still due142602 past their date
Median extension4 months26% of registrations extended
Regulatory cases18on 18 projects

9 in 10 registrations run late here

796 MahaRERA registrations in Sangli and the places within it

36 not yet due106 extended, not yet due602 past even the latest date52 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Sangli

791 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Varad Riddhi Siddhi CapitalsVarad Urban Developers LLPDue Dec 2029——
Vian ExcelusVian DevelopersDue Jun 2029——
Nirmitee Pristine Park Wing ASwastivastu Properties LLPDue Jun 2029——
Parijat SquareG S EngineersDue Dec 2029——
Devkinandan ResidencyPrimevastu RealtyDue Dec 2030——
All 791 projects →
Sangli market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Localities in Sangli

All 25 localities

Most active promoters

  1. Creationproperties7 projects
  2. Deepak Vasantrao Suryawanshi7 projects
  3. Uttam Nagesh Arage7 projects
  4. Anandkumar Baban Rajmane6 projects
  5. Pranav Builders6 projects
  6. Pune Housing and Area Development Board Pune6 projects
  7. Tatyasaheb Sambhaji Khot6 projects
  8. Abhijit Vijaykumar Borgave5 projects
  9. Lagoo Builders And Consultants Pvt Ltd5 projects
  10. Pradeep Shridhar Phadke5 projects

Sangli, in questions

How many projects in Sangli run late?

9 in 10 MahaRERA registrations (708 of 796): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sangli by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology