RERA projects in Vita (M Cl)
35 projects under 35 MahaRERA registrations, registered 2017–2026. 9% have a completion date extended beyond the one promised.
35RERA projects
35Registrations
9Completion still due26 past their completion date
12 monthsMedian extension beyond promised date9% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 1 |
| 2019 | 4 |
| 2020 | 9 |
| 2021 | 3 |
| 2022 | 3 |
| 2023 | 6 |
| 2024 | 3 |
| 2025 | 3 |
| 2026 | 1 |
Projects in Vita (M Cl)
35 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| VenkateshpurramVision Infra | PR1290002601701 | 31 Aug 2026 | 31 Jul 2029 | — | Not yet due | 0 |
| Shivshakti Royal IIGayatri Developers | P53100079908 | 29 Mar 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Riddhi Siddhi ComplexAjinkya Tushar More | P53100079690 | 20 Mar 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| VrindavanSrikrishna Developers | P53100079014 | 31 Jan 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Ayodhya ClassicSanjay Vilas Pawar | P53100077069 | 23 Jul 2024 | 15 Dec 2025 | — | Promised date passed | 0 |
| Vatsalya HeightsArundhati Bhimrao More | P53100066484 | 11 Jun 2024 | 31 May 2026 | — | Promised date passed | 0 |
| Shree Om Sai ResidencyRamchandra Bhimrao Bhingardeve | P53100055208 | 11 Mar 2024 | 15 Jun 2025 | — | Promised date passed | 0 |
| Diamond ArcadePrashant Vasantrao Kirdat Patil | P53100053745 | 28 Nov 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Meridian TowersPrakash Shankarrao Kadam | P53100053589 | 10 Nov 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Jaybhawani ComplexJaybhawani Infra | P53100051696 | 27 Jun 2023 | 31 Dec 2028 | — | Not yet due | 0 |
| Krishnai Villa Row HousingsJogeshwari Enterprises | P53100051444 | 14 Jun 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Vrindavan HomesDhananjay Netaji Patil | P53100051158 | 1 Jun 2023 | 31 Dec 2024 | — | Promised date passed | 0 |
| Horizon TowersMadhav Damodar Rokade | P53100050449 | 12 Apr 2023 | 31 Dec 2024 | 31 Dec 2025 | Extended 12 mo | 0 |
| Samruddhi AppartmentAjinkya Tushar More | P53100047795 | 28 Nov 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Orchid Lifestyle HomeSHEETAL PRAKASH PUNEKAR proprietor of Vision Infra | P53100046782 | 10 Sep 2022 | 15 Jul 2026 | — | Promised date passed | 0 |
| Krishna Raj ComplexAmit Govindrao Bhosale | P53100033435 | 22 Feb 2022 | 12 Aug 2022 | — | Promised date passed | 0 |
| Suprabhat ResidencyKanchan Subhash Divate | P53100032137 | 14 Dec 2021 | 31 Mar 2022 | — | Promised date passed | 0 |
| TathastuAsha Developers | P53100030808 | 14 Sep 2021 | 15 Jul 2024 | — | Promised date passed | 0 |
| Riddhi Siddhi AppartmentAjinkya Tushar More | P53100028168 | 10 Feb 2021 | 30 Jun 2027 | — | Not yet due | 0 |
| North PointNirmann Construction | P53100027208 | 24 Nov 2020 | 30 Apr 2026 | — | Promised date passed | 0 |
| D SquareRaj Developers | P53100025613 | 1 Jul 2020 | 30 Sep 2022 | — | Promised date passed | 0 |
| Patil AvenueRaj Developers | P53100025666 | 1 Jul 2020 | 30 Sep 2022 | — | Promised date passed | 0 |
| Gajanan smrutiBalasaheb Shankar Sutar | P53100025414 | 23 May 2020 | 30 Aug 2020 | 1 Jan 2023 | Extended 29 mo | 0 |
| Reva PrideSudhir Dadasaheb Babar | P53100025360 | 30 Apr 2020 | 30 Jun 2023 | — | Promised date passed | 0 |
| Nirmiti AppartmentShakuntala Narayan Bhagwat | P53100025293 | 5 Apr 2020 | 1 Nov 2022 | — | Promised date passed | 0 |
| Gandhakosh ApartmentsMaheshkumar Pralhad Khilare | P53100024480 | 18 Feb 2020 | 13 Mar 2022 | — | Promised date passed | 0 |
| Leela PrideSuresh Jamatraj Oswal | P53100024296 | 3 Feb 2020 | 15 Sep 2020 | — | Promised date passed | 0 |
| Victoria HomesBalasaheb Rajaram Chavan | P53100024279 | 3 Feb 2020 | 22 Nov 2022 | — | Promised date passed | 0 |
| Sai HeightsSai Developers | P53100023420 | 12 Dec 2019 | 22 Dec 2022 | — | Promised date passed | 0 |
| Pruthvi TowersPruthvi Developers | P53100023295 | 9 Dec 2019 | 22 Dec 2022 | — | Promised date passed | 0 |
| Sai YeshwantSai Yashwant | P53100023227 | 6 Dec 2019 | 22 Dec 2022 | — | Promised date passed | 0 |
| Shivpratap Gold TowerShivpratap Nagari Co Operative Credit Society Ltd. Vita | P53100021540 | 8 Jul 2019 | 30 Jun 2023 | — | Promised date passed | 0 |
| Mayuresh PrideSantosh Dattatray Bidkar | P53100016193 | 23 Apr 2018 | 30 Jun 2022 | — | Promised date passed | 0 |
| Nisarg CityVaibhav Sadashivrao Patil | P53100006628 | 14 Aug 2017 | 31 Jul 2019 | — | Promised date passed | 0 |
| Barsana ResidencyAkshada Yogesh Chavan | P53100000238 | 10 Jul 2017 | 28 Feb 2018 | 26 Feb 2019 | Extended 12 mo | 0 |
Most active promoters
By projects registered here, as named on MahaRERA.
- Ajinkya Tushar More3 projects
- Raj Developers2 projects
- Akshada Yogesh Chavan1 project
- Amit Govindrao Bhosale1 project
- Arundhati Bhimrao More1 project
- Asha Developers1 project
- Balasaheb Rajaram Chavan1 project
- Balasaheb Shankar Sutar1 project
- Dhananjay Netaji Patil1 project
- Gayatri Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology