Atpadi, Sangli
No MahaRERA registration here has an extended completion date on record.
RERA projects1
Registrations1
Completion still due01 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Atpadi
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Gadima Park Phase 1Ajit Builders And Developers | P53100006274 | 14 Aug 2017 | 31 Dec 2019 | 31 Dec 2019 | Promised date passed | 0 |
Most active promoters
- Ajit Builders And Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology