RERA projects in Miraj

662 projects under 666 MahaRERA registrations, registered 2017–2026. 24% have a completion date extended beyond the one promised.

Taluka
662RERA projects
666Registrationssome projects hold several
107Completion still due534 past their completion date
4 monthsMedian extension beyond promised date24% of registrations extended
7Regulatory caseson 7 projects
705Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
2017121
201868
201971
202073
202196
202275
202369
202431
202523
202614

Projects in Miraj

662 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Nirmitee Pristine Park Wing ASwastivastu Properties LLPPR129000260241518 Oct 202630 Jun 2029—Not yet due0
AranyaVerifex Realty LLPPM12900026018208 Sep 202630 Aug 203030 Aug 2030Not yet due0
Elite PrimeShri Venkateshwara BuildconPM12900026017814 Sep 202631 Dec 202831 Dec 2028Not yet due0
Shivnandini ComplexMohite And AssociatesPM129000260159121 Aug 202625 Aug 202825 Aug 2028Not yet due0
Marigold ResidencySiddhant AssociatesPR1290002601250, PR129000260128320 Jul 202631 Dec 202930 Apr 2030Extended 4 mo0
B SquareBalaji ConstructionPR129000260114013 Jul 202630 Jun 202930 Oct 2029Extended 4 mo0
SarangDevrath Structures LLPPM129000260051522 May 202631 Dec 202830 Apr 2029Extended 4 mo0
Surya UniverseSurya Builders And DevelopersPR129000250283916 Mar 202627 Dec 202727 Apr 2028Extended 4 mo0
Shriram VijayLaxmi Udyog SamuhaPM129000250237917 Feb 20261 Jun 20281 Oct 2028Extended 4 mo0
Samrajya SiddhiSiddhinirman Developers LLPPR12900025022919 Feb 202631 Dec 203030 Apr 2031Extended 4 mo0
Trimurti ResidencyVivek Rangrao PatilPR129000250214121 Jan 202631 Mar 202831 Jul 2028Extended 4 mo0
Shanti SagarShravani PropertiesPR129000250207714 Jan 202631 Dec 202830 Apr 2029Extended 4 mo0
Park ViewVisa DevelopersPR12900025019661 Jan 202630 Aug 202830 Dec 2028Extended 4 mo0
Shubha VastuVisa DevelopersPR129000250190729 Dec 202531 Dec 202830 Apr 2029Extended 4 mo0
Khushi OneKhushi Prime Estate Private LimitedP531000810628 Dec 202525 Sep 202825 Jan 2029Extended 4 mo0
Vaje Business SqaureV D Vaje DevelopersPC12900025017005 Dec 202531 May 203030 Sep 2030Extended 4 mo0
Ratna NestsRohan Subhash PatilPR129000250158827 Nov 202531 Dec 202730 Apr 2028Extended 4 mo0
Govind GrandGkm AssociatesPM129000250144011 Nov 20251 Aug 20301 Dec 2030Extended 4 mo0
Psw LandmarkShinde Wadkar DevelopersPM129000250136931 Oct 202531 Dec 202930 Apr 2030Extended 4 mo0
Anand Vihar ResidencyKavita Kishor KulkarniP5310008101514 Oct 202531 Dec 202831 Dec 2028Not yet due0
Shivam PinnacleShree Om DevelopersPM129000250119913 Oct 202531 Dec 202930 Apr 2030Extended 4 mo0
Kaleshwar PridePradeep Shridhar PhadkePM129000250096926 Sep 202531 May 202830 Sep 2028Extended 4 mo0
Irish OrisonChaitanya ConstructionsPM129000250089322 Sep 202531 Dec 203230 Apr 2033Extended 4 mo0
Saiprasad ResidencyShreeram DevelopersPM129000250081616 Sep 202531 Dec 202931 Dec 2029Not yet due0
Varad SiddhivinayakNakshatra InfraPM12900025007114 Sep 202530 Jun 202830 Oct 2028Extended 4 mo0

Other talukas in Sangli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Creationproperties7 projects
  2. Deepak Vasantrao Suryawanshi7 projects
  3. Uttam Nagesh Arage7 projects
  4. Anandkumar Baban Rajmane6 projects
  5. Pranav Builders6 projects
  6. Tatyasaheb Sambhaji Khot6 projects
  7. Abhijit Vijaykumar Borgave5 projects
  8. Lagoo Builders And Consultants Pvt Ltd5 projects
  9. Pradeep Shridhar Phadke5 projects
  10. Pune Housing and Area Development Board Pune5 projects
Data through18 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology