Deedo IDDL-SAN-MIRAJ9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects664
Registrations668some projects hold several
Completion still due105537 past their date
Median extension4 months24% of registrations extended
Regulatory cases7on 7 projects
9 in 10 registrations run late here
668 MahaRERA registrations in Miraj and the places within it
23 not yet due82 extended, not yet due537 past even the latest date26 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Miraj
664 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Varad SiddhivinayakNakshatra Infra | Due Oct 2028, extended 4 mo | — | — |
| Chintamani EliteVitrag Builders & Developers | Due Jul 2029, extended 4 mo | — | — |
| Mahayash ResidencyShirish Shivaji Pandit | Due Aug 2028, extended 4 mo | — | — |
| Deval HorizonRajendra Madhukar Deval | 1 mo late | — | — |
| Shakti PrestigeShakti Buildcon | Due Apr 2031, extended 4 mo | — | — |
| Avr SquareGsj Infrastructure LLP | Due Apr 2028, extended 4 mo | — | — |
| SaptarshiSagar Sumant Kulkarni | Due Apr 2027, extended 4 mo | — | — |
| Universal Trade CenterUniversal Developers | Due Apr 2029, extended 4 mo | — | — |
| Skyline HeritageYatin Dharmendra Modi | Due Apr 2029, extended 4 mo | — | — |
| Narayan HeightsPratham Developers | Due Jun 2029, extended 4 mo | — | — |
| Jeevan AnandSms Life Space Private Limited | Due Apr 2028, extended 4 mo | — | — |
| Kalash ResidencyKaizen Landmarks | Due Apr 2027, extended 4 mo | — | — |
| Shripad Vallabh SiddhiAssociated Developers | Due Feb 2028, extended 4 mo | — | — |
| Saffron CitySaffron Infra | Due Apr 2031, extended 4 mo | — | — |
| Emmanuel IconSantosh Mohan Arawattigi | Due Feb 2028, extended 4 mo | — | — |
| Yelkot VisionYelkot Builders Pvt Ltd | Due Apr 2028, extended 4 mo | — | 3% |
| Sahyadri Pearl | Due Jul 2027 | — | 4% |
| Construction of 34 EWS T/s under PMAY at S.No. 964 P, Bharatnagar, Tal. Miraj, Dist. Sangli, 416310Pune Housing and Area Development Board Pune | Due Apr 2028, extended 4 mo | — | — |
| Shree Krupa CityTatyasaheb Sambhaji Khot | Due Apr 2030, extended 4 mo | — | — |
| Shri GayatriAniket Balasaheb Bhosale | Due Apr 2028, extended 4 mo | — | 12% |
| Sky Vision SquareSky Vision Infra | Due Apr 2028, extended 4 mo | — | — |
| Agrawal Donage HeightsVighnesh Nilesh Agrawal | Due Apr 2029, extended 4 mo | — | — |
| Shiv Sai VandanaS P Builder | Due Feb 2028, extended 4 mo | — | — |
| Shubham ExoticaSrivari Shubha Developers LLP | Due Apr 2028, extended 4 mo | — | — |
| ManidweepVastu Laxmi Developers | Due Apr 2028, extended 4 mo | — | 10% |
Nearby: other talukas in Sangli
Most active promoters
- Creationproperties7 projects
- Deepak Vasantrao Suryawanshi7 projects
- Uttam Nagesh Arage7 projects
- Anandkumar Baban Rajmane6 projects
- Pranav Builders6 projects
- Tatyasaheb Sambhaji Khot6 projects
- Abhijit Vijaykumar Borgave5 projects
- Lagoo Builders And Consultants Pvt Ltd5 projects
- Pradeep Shridhar Phadke5 projects
- Pune Housing and Area Development Board Pune5 projects
Miraj, in questions
How many projects in Miraj run late?
9 in 10 MahaRERA registrations (619 of 668): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Miraj by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology