Miraj, Sangli
Deedo IDDL-SAN-MIRAJ9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects664
Registrations668some projects hold several
Completion still due105537 past their date
Median extension4 months24% of registrations extended
Regulatory cases7on 7 projects
9 in 10 registrations run late here
668 MahaRERA registrations in Miraj and the places within it
23 not yet due82 extended, not yet due537 past even the latest date26 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Miraj
664 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Vian ExcelusVian Developers | Due Jun 2029 | — | — |
| Nirmitee Pristine Park Wing ASwastivastu Properties LLP | Due Jun 2029 | — | — |
| AranyaVerifex Realty LLP | Due Aug 2030 | — | — |
| Elite PrimeShri Venkateshwara Buildcon | Due Dec 2028 | — | — |
| Shivnandini ComplexMohite And Associates | Due Aug 2028 | — | — |
| Marigold ResidencySiddhant Associates | Due Apr 2030, extended 4 mo | — | — |
| B SquareBalaji Construction | Due Oct 2029, extended 4 mo | — | — |
| SarangDevrath Structures LLP | Due Apr 2029, extended 4 mo | — | — |
| Surya UniverseSurya Builders And Developers | Due Apr 2028, extended 4 mo | — | — |
| Shriram VijayLaxmi Udyog Samuha | Due Oct 2028, extended 4 mo | — | — |
| Samrajya SiddhiSiddhinirman Developers LLP | Due Apr 2031, extended 4 mo | — | — |
| Trimurti ResidencyVivek Rangrao Patil | Due Jul 2028, extended 4 mo | — | — |
| Shanti SagarShravani Properties | Due Apr 2029, extended 4 mo | — | — |
| Park ViewVisa Developers | Due Dec 2028, extended 4 mo | — | — |
| Shubha VastuVisa Developers | Due Apr 2029, extended 4 mo | — | — |
| Khushi OneKhushi Prime Estate Private Limited | Due Jan 2029, extended 4 mo | — | — |
| Vaje Business SqaureV D Vaje Developers | Due Sep 2030, extended 4 mo | — | — |
| Ratna NestsRohan Subhash Patil | Due Apr 2028, extended 4 mo | — | — |
| Govind GrandGkm Associates | Due Dec 2030, extended 4 mo | — | — |
| Psw LandmarkShinde Wadkar Developers | Due Apr 2030, extended 4 mo | — | — |
| Anand Vihar ResidencyKavita Kishor Kulkarni | Due Dec 2028 | — | — |
| Shivam PinnacleShree Om Developers | Due Apr 2030, extended 4 mo | — | — |
| Kaleshwar PridePradeep Shridhar Phadke | Due Sep 2028, extended 4 mo | — | — |
| Irish OrisonChaitanya Constructions | Due Apr 2033, extended 4 mo | — | — |
| Saiprasad ResidencyShreeram Developers | Due Dec 2029 | — | — |
Nearby: other talukas in Sangli
Most active promoters
- Creationproperties7 projects
- Deepak Vasantrao Suryawanshi7 projects
- Uttam Nagesh Arage7 projects
- Anandkumar Baban Rajmane6 projects
- Pranav Builders6 projects
- Tatyasaheb Sambhaji Khot6 projects
- Abhijit Vijaykumar Borgave5 projects
- Lagoo Builders And Consultants Pvt Ltd5 projects
- Pradeep Shridhar Phadke5 projects
- Pune Housing and Area Development Board Pune5 projects
Miraj, in questions
How many projects in Miraj run late?
9 in 10 MahaRERA registrations (619 of 668): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Miraj by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology