RERA projects in Vijay Nagar
2 projects under 2 MahaRERA registrations, registered 2018–2020. None has an extended completion date on record.
2RERA projects
2Registrations
1Completion still due1 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 1 |
| 2019 | 0 |
| 2020 | 1 |
Projects in Vijay Nagar
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shree Rajlaxmi MallShree Rajlaxmi Constructions And Builders | P53100025856 | 21 Jul 2020 | 30 Sep 2027 | — | Not yet due | 0 |
| Shree Om GalaxyShree Om Developers | P53100018412 | 30 Oct 2018 | 30 Oct 2021 | — | Promised date passed | 0 |
Other localities in Miraj
- Sangli Miraj Kupwad (M Corp.)565 projects
- Madhavnagar4 projects
- Sangli2 projects
- Haripur1 project
- Narwad1 project
Most active promoters
By projects registered here, as named on MahaRERA.
- Shree Om Developers1 project
- Shree Rajlaxmi Constructions And Builders1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology