RERA projects in Uran Islampur (M Cl)

24 projects under 24 MahaRERA registrations, registered 2017–2026. 17% have a completion date extended beyond the one promised.

24RERA projects
24Registrations
8Completion still due16 past their completion date
12 monthsMedian extension beyond promised date17% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20182
20192
20201
20213
20224
20235
20240
20252
20263

Projects in Uran Islampur (M Cl)

24 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Devkinandan ResidencyPrimevastu RealtyPR12900026021455 Oct 202631 Dec 2030—Not yet due0
Anantganga Housing Complex Antrgat Kedarnath Apartment IslampurAnantganga Housing Complex Antrgat Kedarnath Apartment IslampurPR129000260164925 Aug 202631 Dec 2031—Not yet due0
Vighanharta ComplexMahalaxmi ConstructionsPM12900025022322 Feb 202631 Mar 2029—Not yet due0
Ishan Row HouseMali Engineers And BuildersPR129000250141510 Nov 202531 Mar 2027—Not yet due0
Audumber ResidencyShailesh Prakash DesaiP5310007957817 Mar 202531 May 2028—Not yet due0
Galaxy HeightsMunir Mohamadhusen PatwekarP5310005409627 Dec 202331 Dec 2027—Not yet due0
Royal ResidencySwapn Purti Builders And DevelopersP5310005401519 Dec 202330 Nov 202430 Nov 2025Extended 12 mo0
Amar HeightsAmar Chand AttarP5310005170627 Jun 202330 Jun 2027—Not yet due0
Sai SanskarArm AssociatesP5310005094415 May 202331 Dec 2026—Not yet due0
Mahalaxmi TowerMahalaxmi ConstructionsP531000494318 Feb 202331 Dec 2024—Promised date passed0
Samar PrideVenkateshwara BuildersP5310004769721 Nov 202230 Sep 2023—Promised date passed0
Bhagyashree PlazaM/S Anu ConstructionsP5310003402617 Mar 202231 Dec 2025—Promised date passed0
Shri Datta ComplexMegha Manohar KamerikarP531000330183 Feb 202230 Mar 2023—Promised date passed0
Anantganga Housingg Project Antargat Royal Stone ApartmentBaban Anant PatilP531000324214 Jan 202231 Dec 2023—Promised date passed0
Basharabi PlazaAmar Chand AttarP5310003037617 Aug 202131 Jul 2025—Promised date passed0
Shriram ComplexDurvank Builders And DevelopersP531000298318 Jul 202131 May 202431 Dec 2022Promised date passed0
Malhar ResidencySayali DevelopersP5310002816010 Feb 202130 Jun 202231 Dec 2022Extended 6 mo0
Ananatganga Housing Complex Antargat Sharadban ApartmentBaban Anant PatilP5310002419724 Jan 202030 Dec 2020—Promised date passed0
Fhunda IconNazir Mahamad MujawarP5310002177729 Jul 201930 Dec 2024—Promised date passed0
Shree Riddhi Siddhi Residency Wing -DAnusaya Bapurao PharneP531000203789 Apr 201930 Mar 2025—Promised date passed0
Wakale ArcadeJayant Jaysing NalawadeP5310001756528 Aug 201819 Jul 20221 Jul 2024Extended 24 mo0
Dabholes HeritageDurvank BuildconP5310001690722 Jun 201830 Dec 2022—Promised date passed0
Balaji SamruddhiBalaji BuildconP5310001303312 Sep 201730 Dec 2021—Promised date passed0
Pristine ParkVastushilpa Infra Private LimitedP531000033695 Aug 201731 Dec 201831 Dec 2019Extended 12 mo0

Other localities in Walwa

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Amar Chand Attar2 projects
  2. Baban Anant Patil2 projects
  3. Mahalaxmi Constructions2 projects
  4. Anantganga Housing Complex Antrgat Kedarnath Apartment Islampur1 project
  5. Anusaya Bapurao Pharne1 project
  6. Arm Associates1 project
  7. Balaji Buildcon1 project
  8. Durvank Buildcon1 project
  9. Durvank Builders And Developers1 project
  10. Jayant Jaysing Nalawade1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology