4 projects under 4 MahaRERA registrations, registered 2018–2022. 50% have a completion date extended beyond the one promised.
Locality
4RERA projects
4Registrations
1Completion still due3 past their completion date
29 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 1 |
| 2019 | 0 |
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 2 |
Projects in Jakatwadi
4 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shree Datta SankulKiran Shankarrao Kadam | P52700033848 | 14 Mar 2022 | 31 Jan 2025 | 31 Jan 2027 | Extended 24 mo | 0 |
| Shourya HeightsShourya Developers | P52700032849 | 2 Feb 2022 | 1 Jan 2024 | 1 Jan 2024 | Promised date passed | 0 |
| Rajlaxmi HeightsShri Sai Datta Developers | P52700027568 | 16 Dec 2020 | 1 Jul 2023 | 1 Jul 2023 | Promised date passed | 0 |
| Samarth RecedencyUrmodi Builder & Developers | P52700016134 | 17 Apr 2018 | 30 Sep 2022 | 9 Aug 2025 | Extended 35 mo | 0 |
Other localities in Satara
Most active promoters
By projects registered here, as named on MahaRERA.
- Kiran Shankarrao Kadam1 project
- Shourya Developers1 project
- Shri Sai Datta Developers1 project
- Urmodi Builder & Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology