RERA projects in Jakatwadi

4 projects under 4 MahaRERA registrations, registered 2018–2022. 50% have a completion date extended beyond the one promised.

Locality
4RERA projects
4Registrations
1Completion still due3 past their completion date
29 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20181
20190
20201
20210
20222

Projects in Jakatwadi

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Shree Datta SankulKiran Shankarrao KadamP5270003384814 Mar 202231 Jan 202531 Jan 2027Extended 24 mo0
Shourya HeightsShourya DevelopersP527000328492 Feb 20221 Jan 20241 Jan 2024Promised date passed0
Rajlaxmi HeightsShri Sai Datta DevelopersP5270002756816 Dec 20201 Jul 20231 Jul 2023Promised date passed0
Samarth RecedencyUrmodi Builder & DevelopersP5270001613417 Apr 201830 Sep 20229 Aug 2025Extended 35 mo0

Other localities in Satara

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Kiran Shankarrao Kadam1 project
  2. Shourya Developers1 project
  3. Shri Sai Datta Developers1 project
  4. Urmodi Builder & Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology