RERA projects in Satpur
46 projects under 46 MahaRERA registrations, registered 2017–2026. 2% have a completion date extended beyond the one promised.
46RERA projects
46Registrations
19Completion still due27 past their completion date
6 monthsMedian extension beyond promised date2% of registrations extended
0Regulatory casesnone on MahaRERA's lists
101Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 5 |
| 2018 | 2 |
| 2019 | 0 |
| 2020 | 4 |
| 2021 | 4 |
| 2022 | 7 |
| 2023 | 13 |
| 2024 | 3 |
| 2025 | 4 |
| 2026 | 4 |
Projects in Satpur
46 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Swami Heights ApartmentMayur Sudhakar Mahajan | PR1220002601344 | 29 Jul 2026 | 31 Mar 2031 | — | Not yet due | 0 |
| Vallabh ApparmentDhananjay Nimba Borase | PR1220002601148 | 13 Jul 2026 | 31 Mar 2029 | — | Not yet due | 0 |
| Bhagwati ApartmentNew Swamiraj Construction | PM1220002600040 | 9 Apr 2026 | 1 Feb 2028 | — | Not yet due | 0 |
| Balaji HeightsGeeta Developers | PM1220002502962 | 18 Mar 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Shree Ganesh SrushtiJyk Nirmiti Infra LLP | PM1220002501249 | 16 Oct 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Brahmgiri Park-2Shreevastu Buildcon | PM1220002501162 | 9 Oct 2025 | 31 Mar 2028 | — | Not yet due | 0 |
| Emerald EstateNashik Housing & Area Development Board, Nashik | PM1220002500512 | 7 Aug 2025 | 30 Sep 2030 | — | Not yet due | 0 |
| D-Maps ShivtirthD Map Estates | P51600080458 | 6 Jun 2025 | 31 Jul 2028 | — | Not yet due | 0 |
| Anuveena HeightsVivek Deepak Moule | P51600077677 | 21 Oct 2024 | 30 Jun 2027 | — | Not yet due | 0 |
| Ramkrushna ResidencyRamkrushna Developers | P51600056297 | 25 May 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Brahmgiri ParkShreevastu Buildcon | P51600055245 | 14 Mar 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Sai Park A B C D EVishal Suresh Vidhate | P51600053970 | 18 Dec 2023 | 29 Jun 2026 | — | Promised date passed | 0 |
| Pushkraj NakshatraPushkraj Buildcon | P51600052964 | 6 Oct 2023 | 30 Jun 2026 | — | Promised date passed | 0 |
| Suraj ParkSeva Developers | P51600052435 | 25 Aug 2023 | 1 Jun 2027 | — | Not yet due | 0 |
| Shree Nakshatra ResidencyShree Nakshatra Builders | P51600052206 | 31 Jul 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Gokul 7Gokul Infrastructure | P51600051838 | 7 Jul 2023 | 31 Dec 2024 | — | Promised date passed | 0 |
| Swaraj 1 and 2 BHK HomesKothawale Patil Builders And Developers Pvt. Ltd. | P51600051745 | 27 Jun 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Shree Ganesh ParkB Y Builders and Developers | P51600051448 | 23 Jun 2023 | 31 Dec 2029 | — | Not yet due | 0 |
| Purple Aashray ApartmentKiran Jayantibhai Patel | P51600050208 | 27 Mar 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Crown HeightsCrown Makers Builders and Developers | P51600049748 | 24 Feb 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Mahadeo ShrushtiMahadeo Buildcon | P51600049425 | 8 Feb 2023 | 30 Jun 2025 | — | Promised date passed | 0 |
| Jadhav Park-2Nandkumar Bhagirath Jadhav | P51600049270 | 3 Feb 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Shiv Suman ResidencyS K Construction | P51600049037 | 30 Jan 2023 | 31 Mar 2024 | 30 Sep 2024 | Extended 6 mo | 0 |
| Balaji VillasRahul Bhaskar Musale | P51600048813 | 19 Jan 2023 | 1 Apr 2027 | — | Not yet due | 0 |
| Anmol ResidencyMithila Amol More | P51600047439 | 31 Oct 2022 | 31 Mar 2024 | — | Promised date passed | 0 |
| Tanishaka ApartmentR D Construction | P51600047181 | 11 Oct 2022 | 31 Dec 2023 | — | Promised date passed | 0 |
| Swastik ApartmentShreeraj Builders | P51600046720 | 1 Sep 2022 | 30 Dec 2025 | — | Promised date passed | 0 |
| Aurum ApartmentLahoti Builders And Developers Proprietor Kapil Shyamsundar Lahoti | P51600046156 | 20 Jun 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Radhakrushna ViharS S Construction Proprietor Radhabai Ramkrishna Rokade | P51600045576 | 24 May 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Farhan TowerNational Builders | P51600033583 | 2 Mar 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Thorat HeightsNandkumar Bhagirath Jadhav | P51600033275 | 15 Feb 2022 | 31 Jan 2025 | — | Promised date passed | 0 |
| Gokul 5Gokul Infrastructure | P51600031710 | 8 Nov 2021 | 31 Dec 2022 | — | Promised date passed | 0 |
| Bolkar MajesticGanesh Tukaram Bolkar | P51600030738 | 13 Sep 2021 | 31 Dec 2026 | — | Not yet due | 0 |
| TornaG T Buildcon | P51600030289 | 15 Aug 2021 | 31 Oct 2024 | — | Promised date passed | 0 |
| Vijay HeightsShriram Chindha Patil | P51600028292 | 18 Feb 2021 | 31 Dec 2028 | — | Not yet due | 0 |
| Shree Sai Krupa ApartmentTulsi Developers | P51600027685 | 31 Dec 2020 | 17 Jun 2023 | — | Promised date passed | 0 |
| Krishna ResidencyYash Sandeep Soni | P51600025789 | 16 Jul 2020 | 30 Jun 2023 | — | Promised date passed | 0 |
| Bolkar Nakshatra A B CGanesh Tukaram Bolkar | P51600025548 | 28 Jun 2020 | 1 Jan 2024 | — | Promised date passed | 0 |
| Vraj VillaShree Infra Project | P51600025502 | 8 Jun 2020 | 30 Jun 2023 | — | Promised date passed | 0 |
| Swami DarshanGanesh Tukaram Bolkar | P51600018310 | 23 Oct 2018 | 1 Oct 2024 | — | Promised date passed | 0 |
| Samartha ParkMadhukar Bhagirath Jadhav | P51600016635 | 28 May 2018 | 26 Mar 2024 | — | Promised date passed | 0 |
| Rudraksh ResidencyMugdha Sandeep Bodke | P51600012753 | 7 Sep 2017 | 31 Dec 2019 | — | Promised date passed | 0 |
| Gokul 1Gokul Infrastructure | P51600007108 | 17 Aug 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Klassic HeightsVimla Jashanmal Jagger | P51600007189 | 17 Aug 2017 | 31 Jul 2018 | — | Promised date passed | 0 |
| Crown SquareCrown Makers Builders and Developers | P51600006414 | 14 Aug 2017 | 31 Dec 2020 | — | Promised date passed | 0 |
| Shree Tirumala Hariniwas ApartmentRoongta Homes LLP | P51600001282 | 27 Jul 2017 | 31 Mar 2019 | — | Promised date passed | 0 |
Other localities in Nashik
- Nashik (M Corp.)1,580 projects
- Nashik1,100 projects
- Aanandwali86 projects
- Nashik Road67 projects
- Deolaligaon62 projects
- Deolali (Cb)57 projects
- Jail Road54 projects
- Vihitgaon26 projects
- Bhagur Rural23 projects
- Sansari23 projects
- Chehedi Bk22 projects
- Indiranagar17 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Ganesh Tukaram Bolkar3 projects
- Gokul Infrastructure3 projects
- Crown Makers Builders and Developers2 projects
- Nandkumar Bhagirath Jadhav2 projects
- Shreevastu Buildcon2 projects
- B Y Builders and Developers1 project
- Dhananjay Nimba Borase1 project
- D Map Estates1 project
- Geeta Developers1 project
- G T Buildcon1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology