RERA projects in Satpur

46 projects under 46 MahaRERA registrations, registered 2017–2026. 2% have a completion date extended beyond the one promised.

46RERA projects
46Registrations
19Completion still due27 past their completion date
6 monthsMedian extension beyond promised date2% of registrations extended
0Regulatory casesnone on MahaRERA's lists
101Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20175
20182
20190
20204
20214
20227
202313
20243
20254
20264

Projects in Satpur

46 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Swami Heights ApartmentMayur Sudhakar MahajanPR122000260134429 Jul 202631 Mar 2031—Not yet due0
Vallabh ApparmentDhananjay Nimba BorasePR122000260114813 Jul 202631 Mar 2029—Not yet due0
Bhagwati ApartmentNew Swamiraj ConstructionPM12200026000409 Apr 20261 Feb 2028—Not yet due0
Balaji HeightsGeeta DevelopersPM122000250296218 Mar 202631 Dec 2030—Not yet due0
Shree Ganesh SrushtiJyk Nirmiti Infra LLPPM122000250124916 Oct 202531 Dec 2029—Not yet due0
Brahmgiri Park-2Shreevastu BuildconPM12200025011629 Oct 202531 Mar 2028—Not yet due0
Emerald EstateNashik Housing & Area Development Board, NashikPM12200025005127 Aug 202530 Sep 2030—Not yet due0
D-Maps ShivtirthD Map EstatesP516000804586 Jun 202531 Jul 2028—Not yet due0
Anuveena HeightsVivek Deepak MouleP5160007767721 Oct 202430 Jun 2027—Not yet due0
Ramkrushna ResidencyRamkrushna DevelopersP5160005629725 May 202431 Dec 2026—Not yet due0
Brahmgiri ParkShreevastu BuildconP5160005524514 Mar 202431 Dec 2028—Not yet due0
Sai Park A B C D EVishal Suresh VidhateP5160005397018 Dec 202329 Jun 2026—Promised date passed0
Pushkraj NakshatraPushkraj BuildconP516000529646 Oct 202330 Jun 2026—Promised date passed0
Suraj ParkSeva DevelopersP5160005243525 Aug 20231 Jun 2027—Not yet due0
Shree Nakshatra ResidencyShree Nakshatra BuildersP5160005220631 Jul 202331 Dec 2025—Promised date passed0
Gokul 7Gokul InfrastructureP516000518387 Jul 202331 Dec 2024—Promised date passed0
Swaraj 1 and 2 BHK HomesKothawale Patil Builders And Developers Pvt. Ltd.P5160005174527 Jun 202331 Dec 2027—Not yet due0
Shree Ganesh ParkB Y Builders and DevelopersP5160005144823 Jun 202331 Dec 2029—Not yet due0
Purple Aashray ApartmentKiran Jayantibhai PatelP5160005020827 Mar 202331 Dec 2025—Promised date passed0
Crown HeightsCrown Makers Builders and DevelopersP5160004974824 Feb 202331 Dec 2026—Not yet due0
Mahadeo ShrushtiMahadeo BuildconP516000494258 Feb 202330 Jun 2025—Promised date passed0
Jadhav Park-2Nandkumar Bhagirath JadhavP516000492703 Feb 202331 Dec 2027—Not yet due0
Shiv Suman ResidencyS K ConstructionP5160004903730 Jan 202331 Mar 202430 Sep 2024Extended 6 mo0
Balaji VillasRahul Bhaskar MusaleP5160004881319 Jan 20231 Apr 2027—Not yet due0
Anmol ResidencyMithila Amol MoreP5160004743931 Oct 202231 Mar 2024—Promised date passed0
Tanishaka ApartmentR D ConstructionP5160004718111 Oct 202231 Dec 2023—Promised date passed0
Swastik ApartmentShreeraj BuildersP516000467201 Sep 202230 Dec 2025—Promised date passed0
Aurum ApartmentLahoti Builders And Developers Proprietor Kapil Shyamsundar LahotiP5160004615620 Jun 202231 Dec 2025—Promised date passed0
Radhakrushna ViharS S Construction Proprietor Radhabai Ramkrishna RokadeP5160004557624 May 202231 Dec 2024—Promised date passed0
Farhan TowerNational BuildersP516000335832 Mar 202231 Dec 2025—Promised date passed0
Thorat HeightsNandkumar Bhagirath JadhavP5160003327515 Feb 202231 Jan 2025—Promised date passed0
Gokul 5Gokul InfrastructureP516000317108 Nov 202131 Dec 2022—Promised date passed0
Bolkar MajesticGanesh Tukaram BolkarP5160003073813 Sep 202131 Dec 2026—Not yet due0
TornaG T BuildconP5160003028915 Aug 202131 Oct 2024—Promised date passed0
Vijay HeightsShriram Chindha PatilP5160002829218 Feb 202131 Dec 2028—Not yet due0
Shree Sai Krupa ApartmentTulsi DevelopersP5160002768531 Dec 202017 Jun 2023—Promised date passed0
Krishna ResidencyYash Sandeep SoniP5160002578916 Jul 202030 Jun 2023—Promised date passed0
Bolkar Nakshatra A B CGanesh Tukaram BolkarP5160002554828 Jun 20201 Jan 2024—Promised date passed0
Vraj VillaShree Infra ProjectP516000255028 Jun 202030 Jun 2023—Promised date passed0
Swami DarshanGanesh Tukaram BolkarP5160001831023 Oct 20181 Oct 2024—Promised date passed0
Samartha ParkMadhukar Bhagirath JadhavP5160001663528 May 201826 Mar 2024—Promised date passed0
Rudraksh ResidencyMugdha Sandeep BodkeP516000127537 Sep 201731 Dec 2019—Promised date passed0
Gokul 1Gokul InfrastructureP5160000710817 Aug 201731 Dec 2018—Promised date passed0
Klassic HeightsVimla Jashanmal JaggerP5160000718917 Aug 201731 Jul 2018—Promised date passed0
Crown SquareCrown Makers Builders and DevelopersP5160000641414 Aug 201731 Dec 2020—Promised date passed0
Shree Tirumala Hariniwas ApartmentRoongta Homes LLPP5160000128227 Jul 201731 Mar 2019—Promised date passed0

Other localities in Nashik

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Ganesh Tukaram Bolkar3 projects
  2. Gokul Infrastructure3 projects
  3. Crown Makers Builders and Developers2 projects
  4. Nandkumar Bhagirath Jadhav2 projects
  5. Shreevastu Buildcon2 projects
  6. B Y Builders and Developers1 project
  7. Dhananjay Nimba Borase1 project
  8. D Map Estates1 project
  9. Geeta Developers1 project
  10. G T Buildcon1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology