Skip to content

Pathardi, Nashik

Deedo IDDL-NSK-PATHARDI

7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects37
Registrations37
Completion still due2215 past their date
Median extension4 months41% of registrations extended
Regulatory cases0none on MahaRERA's lists

7 in 10 registrations run late here

37 MahaRERA registrations in Pathardi

3 completed7 not yet due15 extended, not yet due12 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Pathardi

37 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Vaishnavi Mountain LeafVaishnavi DevelopersDue Mar 2030——
Sai BalajiSaidev ConstructionDue Dec 2030——
Uma AvenueSwastik BlissDue Mar 2029——
Raghunadan HeightsPsbb ConstructionDue Jun 2029——
Moreshwar ParkNew Shreeram BuildersDue Aug 2029——
All 37 projects →
Pathardi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Maheshwar Enterprises2 projects
  2. Appulkumar Vithalbhai Rakholiya1 project
  3. Ashwinbhai Bavanjibhai Bokarwadia1 project
  4. Dk Construction1 project
  5. Gajanan Hights Co Op Hsg Soc Ltd1 project
  6. Govinda Construction1 project
  7. Haridarshan Developers1 project
  8. Jaap Builders & Developers1 project
  9. J P Buildcon1 project
  10. Kamal Buildtech1 project

Pathardi, in questions

How many projects in Pathardi run late?

7 in 10 MahaRERA registrations (27 of 37): their completion date was extended or has passed, data through 5 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Pathardi by Deedo. Medians on fewer than 3 deeds are not shown.

Data through5 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology