8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1,251
Registrations1,260some projects hold several
Completion still due388872 past their date
Median extension4 months28% of registrations extended
Regulatory cases26on 17 projects

8 in 10 registrations run late here

1,260 MahaRERA registrations in Nashik (M Corp.)

146 completed119 not yet due266 extended, not yet due729 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik (M Corp.)

1,251 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Mangalam HeightsRajshree DevelopersDue Dec 2027——
Raghunandan ParkKiran Jagannath KataleDue Jun 2031——
Shree Dattaraaj LandmarkJaybhave BuildconDue Mar 2030——
Shree Laxmi NarayanC K BuildconDue Dec 2028——
Padmashree ParkPadma Omshree Builders Private LimitedDue Mar 2029——
All 1,251 projects →
Nashik (M Corp.) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Jay Developers10 projects
  2. Sanklecha Construction Private Limited10 projects
  3. Govinda Construction7 projects
  4. Hariom Group7 projects
  5. Sanklecha Construction Private Limited7 projects
  6. Ravindra Developers Pvt Ltd5 projects
  7. Shreeji Life Space5 projects
  8. Apurva Builders And Developers4 projects
  9. Ashoka Infraways Limited4 projects
  10. Nashik Housing And Area Development Board4 projects

Nashik (M Corp.), in questions

How many projects in Nashik (M Corp.) run late?

8 in 10 MahaRERA registrations (995 of 1,260): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik (M Corp.) by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology