9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects24
Registrations24
Completion still due519 past their date
Median extension12 months21% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

24 MahaRERA registrations in Indiranagar

3 completed4 extended, not yet due17 past even the latest date

Extended registrations moved their completion date by a median of 12 months.

Projects in Indiranagar

24 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Aakar SolitaireRavi Aakar Group Of ConstructionDue Apr 2028, extended 4 mo——
Aakar CrestAakar Developers6 mo late——
Perfect Rama ResidencyPerfect BuildwellCompleted——
VasantpushpaKtg AssociatesCompleted—25%
Pushkar Co-Op. Hsg. Soc. Ltd.Raviraj Buildtech2 yrs 9 mo late—17%
All 24 projects →
Indiranagar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Aakar Developers1 project
  2. Abhay Chandmal Jain1 project
  3. Amit Gangadhar Jadhav1 project
  4. Amma Builders And Developers1 project
  5. Atul Anil Nerpagar1 project
  6. Jk Buildcon1 project
  7. Jk Infrastructures1 project
  8. Ktg Associates1 project
  9. Laxmi Consructions1 project
  10. Nitin Amrutkar & Associates1 project

Indiranagar, in questions

How many projects in Indiranagar run late?

9 in 10 MahaRERA registrations (21 of 24): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Indiranagar by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology