Deedo IDDL-NSK-NASHIK

3 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects4,186in 103 localities
Registrations4,237some projects hold several
Completion still due1,3082,557 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

7 in 10 registrations run late here

4,237 MahaRERA registrations in Nashik and the places within it

376 completed400 not yet due899 extended, not yet due2,190 past even the latest date372 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,186 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Sai Pujan Co Operative Housing SocietyYogita Ashish ChhatrolaDue Dec 2029——
Swami ParadiseSamarth GroupDue Dec 2029——
Aureon CrestAureon ConstructionsDue Mar 2029——
Shree Dattaraaj LandmarkJaybhave BuildconDue Mar 2030——
RadheshyamMeeraben Bharatbhai ViramgamaDue Dec 2028——
Vrundavan PrideGhanshyambhai Gokalbhai ViramgamaDue Dec 2028——
Sai BalajiSaidev ConstructionDue Dec 2030——
Vishwaraj Co-op. housing society LtdNarayan InfraDue Dec 2031——
Samarth EliteVinayaka DevelopersDue Dec 2030——
Shree Laxmi NarayanC K BuildconDue Dec 2028——
Uma AvenueSwastik BlissDue Mar 2029——
Atmarupa ResidencyAnuj InfraDue Mar 2028——
Autograph By ShreejiSai Sahara DevelopersDue Jun 2032——
D-Map’s Shivtirth-BD Map EstatesDue Sep 2031——
Ashapuri KasturiRishi Builders & DevelopersDue Aug 2030——
Krushnamurthy ApartmentAtreya ConstructionDue Dec 2028——
Shraddha EmpireShraddha Empire Builders And DevelopersDue Dec 2029——
Suvik PalacioSuvik Buildcon LLPDue Mar 2034——
Fortunes Emerald ParkFortune Homes LLPDue Dec 2033——
Govind NandanShree S P BuildconDue Mar 2030——
Quillion Residencies at Quillion Park - Phase 2Viraj Estates Private LimitedDue Dec 2032——
Sara Serenity ApartmentSara Developers & AssociatesDue Mar 2029——
Shree VishvaDilip Vishwanath GodseDue Dec 2031——
Shriram ParkRambhoomi Developers LLPDue Jun 2029——
Akshar GardenSunrise BuildconDue Mar 2030——

Most active promoters

  1. Roongta Homes LLP26 projects
  2. Kbc Global Limited19 projects
  3. Jay Developers17 projects
  4. Nashik Housing and Area Development Board12 projects
  5. Sanklecha Construction Private Limited12 projects
  6. Om Developers11 projects
  7. Shah Builders And Developers11 projects
  8. Sun Infrastructures Pvt Ltd11 projects
  9. M/S Shweta Infrastructure & Housing (I) Pvt. Ltd.10 projects
  10. Shreeji Life Space10 projects
Data through24 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology