Kasbe Vani, Nashik
Deedo IDDL-NSK-KASBEVANI10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects7
Registrations7
Completion still due16 past their date
Median extension4 months14% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
7 MahaRERA registrations in Kasbe Vani
1 extended, not yet due6 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Kasbe Vani
7 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shankheshwar Ro-BunglowsS. S. Creation | Due Apr 2027, extended 4 mo | — | 10% |
| Nirmala Vihar 2Deepchhaya Constructions | Completed | — | 75% |
| Golden Row BunglowS S Flora | Completed | — | — |
| Suvarna Green ParkSuvarna Buildon | Completed | — | — |
| Nirmala ViharDeepali Anand Sisodiya | Completed | — | 92% |
Nearby: other villages in Dindori
Most active promoters
- Anand Parasmal Sisodiya1 project
- Deepali Anand Sisodiya1 project
- Deepchhaya Constructions1 project
- Mahendrakumar Bhavarilal Parakh1 project
- S. S. Creation1 project
- S S Flora1 project
- Suvarna Buildon1 project
Kasbe Vani, in questions
How many projects in Kasbe Vani run late?
10 in 10 MahaRERA registrations (7 of 7): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Kasbe Vani by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology