RERA projects in Dindori

8 projects under 8 MahaRERA registrations, registered 2021–2025. None has an extended completion date on record.

8RERA projects
8Registrations
5Completion still due3 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20213
20221
20232
20241
20251

Projects in Dindori

8 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Nature's PrideBurad BuildersPR122000250154424 Nov 202531 Oct 2027—Not yet due0
Dindori Trade CenterShree Laxmi Balaji BuildconP5160005574716 Apr 202431 Dec 2027—Not yet due0
B SquareBurad BuildconP5160005338127 Oct 202331 Dec 2026—Not yet due0
Sai AanandAshwini BuildconP516000528345 Oct 202331 Dec 2028—Not yet due0
Hari AanganS. S. ConstructionsP5160004711310 Oct 202230 Sep 2025—Promised date passed0
Kmc Business ParkKmc BuildconP516000317639 Nov 202131 Dec 2026—Not yet due0
Siddhesh ApartmentSiddhesh DevelopersP5160003121511 Oct 20211 Aug 2024—Promised date passed0
Vrindavan HeightsSachin Subhash GaikwadP5160003045525 Aug 202131 Mar 2024—Promised date passed0

Other localities in Dindori

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Ashwini Buildcon1 project
  2. Burad Buildcon1 project
  3. Burad Builders1 project
  4. Kmc Buildcon1 project
  5. Sachin Subhash Gaikwad1 project
  6. Shree Laxmi Balaji Buildcon1 project
  7. Siddhesh Developers1 project
  8. S. S. Constructions1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology