RERA projects in Manmad (M Cl)

2 projects under 2 MahaRERA registrations, registered 2017–2018. 50% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
0Completion still due2 past their completion date
17 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20181

Projects in Manmad (M Cl)

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Sai City CenterSai Ganesh BuildconP516000158964 Apr 201823 Jan 202330 Jun 2024Extended 17 mo0
Pamko SmruteeSatish Balkrishna ParanjapeP516000041448 Aug 201715 Apr 202215 Apr 2022Promised date passed0

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Sai Ganesh Buildcon1 project
  2. Satish Balkrishna Paranjape1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology