Sai City Center
LapsedManmad (M Cl), Nashik 423104 |Promoter: Sai Ganesh Buildcon
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Commercial
- Status on MahaRERA
- Lapsed
- Buildings
- 1
- Land area for this project
- 3,750 sq m (40,365 sq ft)
- Permissible built-up area
- 5,156 sq m (55,500 sq ft)
- Sanctioned built-up area
- 5,156 sq m (55,500 sq ft)
- Address
- Survey No 4/1, Nandgaon Road, Opp-MarketPIN 423104
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year and 5 months
The latest completion date on record passed 2 years and 4 months ago.
- Registered
- 4 Apr 2018
- Promised
- 23 Jan 2023
- Revised
- 30 Jun 2024
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600015896 | 4 Apr 2018 | 23 Jan 2023 | 30 Jun 2024 | Sai Ganesh Buildcon | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Sai City Center | 8 | — |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 units registered
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| Open Space | 0 | 0 | 0 | 0 | 16 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Sai City Center
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
35 documents held by Deedo, 37 filings listed on MahaRERA's project page
Others
- Other21 Mar 2018ViewSource
- Other21 Mar 2018ViewSource
- Other21 Mar 2018ViewSource
- Other21 Mar 2018ViewSource
- Other21 Mar 2018ViewSource
- Other22 Mar 2018ViewSource
- Other27 Mar 2018ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other24 Jan 2024ViewSource
- Other31 Jan 2024ViewSource
- Other31 Jan 2024ViewSource
- Other8 Feb 2024ViewSource
- Other8 Feb 2024ViewSource
- Other8 Feb 2024ViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
Document library
- Declaration in FORM BFORM B.pdf · uploaded 21 Mar 2018View
- Commencement Certificates / NA Order for plotted developmentcommencment.pdf · uploaded 21 Mar 2018View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer certificate.pdf · uploaded 21 Mar 2018View
- Building Plan Approval (IOD)scan070.pdf · uploaded 21 Mar 2018View
- Copy of the legal title reportTital AND SearcH REPORT.pdf · uploaded 21 Mar 2018View
- Proforma of Allotment letterFORMAT OF AGREEMENT TO SALE.pdf · uploaded 21 Mar 2018View
- Status of Formation of Legal Entitysai ganesh partnership.pdf · uploaded 21 Mar 2018View
- Otherscan0711-min.pdf · uploaded 21 Mar 2018View
- Details of encumbrancesenecumbrances certificate.pdf · uploaded 22 Mar 2018View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE.pdf · uploaded 27 Mar 2018View
- Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)FORM 5 31 03 2018.pdf · uploaded 24 Jan 2024View
- Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 31 03 2019.pdf · uploaded 24 Jan 2024View
- Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 31 03 2020.pdf · uploaded 24 Jan 2024View
- Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 31 03 2021.pdf · uploaded 24 Jan 2024View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 AS ON 31 03 2018.pdf · uploaded 24 Jan 2024View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 AS ON 31 03 2018.pdf · uploaded 24 Jan 2024View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 AS ON 31 03 2021.pdf · uploaded 24 Jan 2024View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 AS ON 31 03 2022.pdf · uploaded 24 Jan 2024View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 AS ON 31 03 2023.pdf · uploaded 24 Jan 2024View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FROM 2 31 03 2018.pdf · uploaded 24 Jan 2024View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FROM 2 31 03 2019.pdf · uploaded 24 Jan 2024View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FROM 2 31 03 2020.pdf · uploaded 24 Jan 2024View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FROM 2 31 03 2021.pdf · uploaded 24 Jan 2024View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FROM 2 31 03 2022.pdf · uploaded 24 Jan 2024View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 30 06 2022.pdf · uploaded 24 Jan 2024View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 30 09 2022.pdf · uploaded 24 Jan 2024View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 31 03 2023.pdf · uploaded 24 Jan 2024View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 AS ON 31 03 2019.pdf · uploaded 31 Jan 2024View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 AS ON 31 03 2020.pdf · uploaded 31 Jan 2024View
- Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 31 03 2022.pdf · uploaded 8 Feb 2024View
- Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 31 03 2023.pdf · uploaded 8 Feb 2024View
- Disclosure of sold/ booked inventoryDisclosure of sold unsold inventory.pdf · uploaded 8 Feb 2024View
Promoter documents
Technical documents
- Building Plan Approvalscan070.pdfView
Other legal documents
- Otherscan0711-min.pdfView
Proforma allotment letter
- Proforma allotment letterFORMAT OF AGREEMENT TO SALE.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Manmad (M Cl), Nandgaon taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
SURVEY NO 4/1
Boundaries
- North
- Lale Shindes Property
- South
- Nandgaon Road
- East
- Varad Comlpex
- West
- Malegaon Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Dhiraj Walunj | — |
| Chartered accountant | Mukesh Khond And Co | — |
| Chartered accountant | Tushar Sudhakar Lokhande Bhalgat Bothara And Associates | — |
| Engineer | Ganesh Kawale | — |
| Engineer | Prasad Dhirve | — |
| Other | Farida Mithaiwala | — |
Source: MahaRERA project page. Contact details are not shown.