Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Lapsed

P51600015896

Sai City Center · Manmad (M Cl), Nashik · Sai Ganesh Buildcon

Promised for 23 Jan 2023, extended once to 30 Jun 2024 — and that date has passed without the project marked complete on MahaRERA.

3 years and 9 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 23 Jan 2023 to 30 Jun 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 35

Title report21 Mar 2018View
Commencement certificate21 Mar 2018View
Form B21 Mar 2018View
Form 221 Mar 2018View
Other21 Mar 2018View
Encumbrance details22 Mar 2018View
Form 127 Mar 2018View
Registration certificate9 Sep 2021View
Show all 35 documents
Form 124 Jan 2024View
Form 124 Jan 2024View
Form 124 Jan 2024View
Form 124 Jan 2024View
Form 224 Jan 2024View
Form 224 Jan 2024View
Form 224 Jan 2024View
Form 224 Jan 2024View
Form 224 Jan 2024View
Form 224 Jan 2024View
Form 224 Jan 2024View
Form 224 Jan 2024View
Form 524 Jan 2024View
Form 524 Jan 2024View
Form 524 Jan 2024View
Form 524 Jan 2024View
Form 131 Jan 2024View
Form 131 Jan 2024View
Other8 Feb 2024View
Form 58 Feb 2024View
Form 58 Feb 2024View
Extension certificate15 Feb 2024View
OtherView
OtherView
Building planView
Allotment letterView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51600015896

Is Sai City Center delayed?

Yes. MahaRERA records a promised completion of 23 Jan 2023, revised to 30 Jun 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51600015896. The completion date moved from 23 Jan 2023 to 30 Jun 2024.

Who is the promoter?

MahaRERA records Sai Ganesh Buildcon as the promoter of P51600015896.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51600015896.

Answers are generated from the record.

Data through25 Oct 2026, 02:12SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology