5 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects2
Registrations2
Completion still due11 past their date
Median extension75 months50% of registrations extended
Regulatory cases0none on MahaRERA's lists

5 in 10 registrations run late here

2 MahaRERA registrations in Sangameshwar (Ct)

1 not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 75 months.

Projects in Sangameshwar (Ct)

2 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Sanket HeightsShree Sanket DevelopersDue Dec 2026—19%
Shree Sanket EmpireShree Sanket DevelopersCompleted, extended 6 yrs 3 mo—52%
Sangameshwar (Ct) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Shree Sanket Developers2 projects

Sangameshwar (Ct), in questions

How many projects in Sangameshwar (Ct) run late?

5 in 10 MahaRERA registrations (1 of 2): their completion date was extended or has passed, data through 7 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sangameshwar (Ct) by Deedo. Medians on fewer than 3 deeds are not shown.

Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology