Bhagur (M Cl), Nashik

No MahaRERA registration here has an extended completion date on record.

RERA projects7
Registrations7
Completion still due16 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases0none on MahaRERA's lists
Bhagur (M Cl) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

7 in 10 registrations run late here

7 MahaRERA registrations in Bhagur (M Cl)

1 completed1 not yet due5 past even the latest date

Projects in Bhagur (M Cl)

7 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Cozy NestKirit Infraspaces1 yr 10 mo late——
Madhav ParkAshwini Dipak DholiDue Dec 2026—22%
Arkk Pushp Phase IIVijay Laljibhai Chheda4 mo late—8%
Anmol Enclave Phase IISaibaba Realtors1 yr 4 mo late——
Arkk Estate Phase IIArkk Infrastructure2 yrs 4 mo late——
Maruti HeightsChandrashekar Rambhau Mhaske1 yr 4 mo late—0%
Tirupati Garden Phase IIIRiddhi Siddhi ConstructionsCompleted——

Most active promoters

  1. Arkk Infrastructure1 project
  2. Ashwini Dipak Dholi1 project
  3. Chandrashekar Rambhau Mhaske1 project
  4. Kirit Infraspaces1 project
  5. Riddhi Siddhi Constructions1 project
  6. Saibaba Realtors1 project
  7. Vijay Laljibhai Chheda1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology