Skip to content

Khambale, Nashik

Deedo IDDL-NSK-KHAMBALE

No MahaRERA registration here runs late on record.

RERA projects1
Registrations1
Completion still due10 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases0none on MahaRERA's lists

No registration here runs late on record

1 MahaRERA registration in Khambale

1 not yet due

Projects in Khambale

1 project registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Hanging EdenIshanya BuildconDue Mar 2032——
Khambale market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Ishanya Buildcon1 project

Khambale, in questions

How many projects in Khambale run late?

0% of MahaRERA registrations (0 of 1): their completion date was extended or has passed, data through 7 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Khambale by Deedo. Medians on fewer than 3 deeds are not shown.

Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology